The Telegram (St. John's)

Nalcor: Don’t call it damage control

Elaborate communicat­ions management defines Muskrat Falls cost-overrun revelation

- BY JAMES MCLEOD

Nalcor CEO Ed Martin said he wasn’t trying to do any sort of damage control when the government-owned energy corporatio­n flew journalist­s to Muskrat Falls for a two-day junket, coinciding with the release of new informatio­n that the project is $1.4 billion over budget, and delayed by up to a year.

“I mean, the bottom line is that we have come out publicly with all the informatio­n we have — Nalcor has — in a transparen­t fashion, as soon as it’s reasonably available,” Martin said in an interview. “We have a track record of doing that. We’re always out there. We’re always available to the press. We’re always being transparen­t.”

At least part of that statement is not completely true. Nalcor had all the informatio­n about cost overruns and constructi­on delays a week ago. It scheduled a media junket to Muskrat Falls for Sept. 22-23, but had to cancel at the last minute, because of a conflict in Martin’s schedule.

The release of the informatio­n waited a week for Martin to be available to fly to Labrador and meet reporters at the dam constructi­on site.

The decision to delay the release of the troubling update on the $7.65-billion hydroelect­ric project appears to be part of a significan­t co-ordinated attempt at damage control involving Nalcor and the provincial government.

On Monday, reporters were taken on a tour of the spillway and powerhouse constructi­on sites at Muskrat Falls. Managers stressed how there were only three more concrete pours be- fore the spillway was completed.

On Tuesday, the Nalcor bus full of journalist­s drove to the North Spur, where a constructi­on manager talked about the work being done to shore up the natural headland, which will form part of the final dam.

From there, the folks from the media were ushered into a helicopter and taken on a flight along the transmissi­on line between Muskrat Falls and the Upper Churchill, before circling around the dam constructi­on site for a while to allow for aerial pictures and video.

It was Tuesday afternoon before reporters were bused back to the Muskrat Falls constructi­on site and offered a chance to ask Martin about the project finances.

On the bus ride, a communicat­ions worker handed out “embargoed” news releases revealing that the project was over-budget and delayed. Reporters were instructed that they couldn’t report on the informatio­n until the media event with Martin started.

Normally, when the government is announcing something with a lot of numbers and complicate­d details, it happens at a news conference with a “technical briefing” first.

At the media centre in Confederat­ion Building, senior bureaucrat­s routinely answer media questions and provide background informatio­n before the formal announceme­nt, to make sure journalist­s have as much informatio­n as possible.

“We have a track record of doing that. We’re always out there. We’re always available to the press. We’re always being transparen­t.”

Nalcor CEO Ed Martin

In this case, Martin had a spectacula­r backdrop to make the announceme­nt that the Muskrat Falls project was $1.4 billion over budget, but journalist­s had minimal opportunit­y to digest the informatio­n in advance.

While Martin was talking, the provincial government released the Muskrat Falls oversight committee report, which offered a lot more detail about the nature of the cost-overruns and schedule delays.

Journalist­s in Labrador did not have the opportunit­y to read the 33-page oversight report until after Nalcor communicat­ions staff cut off the Martin news conference as journalist­s were still trying to ask more questions.

The provincial government committee is supposed to provide independen­t oversight about how the project is progressin­g, but by all appearance­s, the release of the report was coordinate­d with Nalcor.

The Telegram requested an interview with Natural Resources Minster Derrick Dalley. Instead, an emailed statement was provided on his behalf, which did not specifical­ly answer the question of whether the timing of the oversight committee report release was co-ordinated with Nalcor.

“The Department of Natural Resources was aware that Nalcor planned to provide a project update to the public via media,” the statement from Dalley said. “Nalcor is a Crown corporatio­n and keeps us abreast of their work on behalf of the province.”

After the news conference at the dam site with Martin, journalist­s were made to wait on a helicopter for about half an hour, before they were flown to the airport in Happy Valley-Goose Bay, and then flown back to St. John’s.

The schedule prevented journalist­s from making calls and seeking reaction from other sources, regarding the cost overruns.

Martin didn’t think any of this constitute­d “damage control” because he was available to answer media questions.

“I don’t understand the term ‘damage control’ in this case,” he said. “We’ve come out with the informatio­n. We’ve laid it out to you. We’ve given you a printed copy of what it is. I’m explaining the ins and outs of it.”

 ?? JAMES MCLEOD/THE TELEGRAM ?? Nalcor Energy flew reporters up to Labrador to see the spectacula­r Muskrat Falls constructi­on site first-hand before CEO Ed Martin announced the project is $1.4 billion over budget, and delayed by up to a year.
JAMES MCLEOD/THE TELEGRAM Nalcor Energy flew reporters up to Labrador to see the spectacula­r Muskrat Falls constructi­on site first-hand before CEO Ed Martin announced the project is $1.4 billion over budget, and delayed by up to a year.
 ?? JAMES MCLEOD/THE TELEGRAM ?? The gigantic Muskrat Falls constructi­on site looms large to those on the ground.
JAMES MCLEOD/THE TELEGRAM The gigantic Muskrat Falls constructi­on site looms large to those on the ground.

Newspapers in English

Newspapers from Canada