Times Colonist

SITE C TIMELINE

-

• 1980 — B.C. Hydro applies to build the dam, following engineerin­g studies that began in 1971. • 1981-1983 — B.C. Utilities Commission deems the project acceptable, but after a series of hearings, calls for more informatio­n on future energy demand and alternativ­e ways to meet it. • 1993 — B.C. Hydro president and chief executive officer Marc Eliesen tells Vancouver Sun that Site C will not be built in the next 10 to 15 years due to financial and environmen­tal concerns. • 2014 — Federal-provincial joint review panel finds Site C appears to be most economic solution to meet future power demand, but says true cost is unknown. • December 2014 — Then-premier Christy Clark gives green light to project. • Summer 2015 — Constructi­on begins. • March 2016 — Court orders protesters who camped at the site for two months to leave. • May 2016 — Royal Society of Canada joins 250 academics calling on federal government to stop project. • May 2016 — Federal government says it won’t revisit a project that has already been approved. • July 2016 — Site C challenged in B.C. Supreme Court petition over frog and tadpole relocation. Department of Fisheries and Oceans and Transport Canada authorize B.C. Hydro to move forward with Site C. • August 2016 — Amnesty Internatio­nal calls for work to stop. • September 2016 — Two First Nations from Treaty 8 territory — Prophet River and West Moberly — argue in federal court that the project violates constituti­onally protected treaty rights. • September 2016 — B.C. Court of Appeal rules against Peace Valley Landowner Associatio­n in its fight against Site C. It rules ministries of Environmen­t and Forestry don’t have to consider all 50 recommenda­tions of an environmen­tal assessment report in issuing an environmen­tal assessment certificat­e. • December 2016 — Farmers Ken and Arlene Boon are told their home will be seized to make way for the project. • January 2017 — Federal court dismisses Prophet River and West Moberly legal challenge. • February — A 400-metre tension crack appears in ground near project, delaying work. • May — Second tension crack appears on left bank of river, delaying constructi­on. • June — B.C. NDP Leader John Horgan and B.C. Green Party Leader Andrew Weaver agree to refer Site C for independen­t review by the B.C. Utilities Commission, as part of power-sharing pact. • July — B.C. NDP sworn in as government. • August — Energy Minister Michelle Mungall commission­s B.C. Utilities Commission to review project’s financial viability. • October — B.C. Hydro says it will miss a critical river-diversion milestone, adding about $610 million to the budget. • November — B.C. Utilities Commission report finds project is over budget and behind schedule. It doesn’t make a recommenda­tion about whether the province should proceed or cancel the dam, but says terminatin­g it would cost $1.8 billion, while completing it could cost $10 billion. It says wind or geothermal projects could provide energy at the same or lower cost. • November — Premier John Horgan says the project could face ongoing legal battles over Indigenous rights and may end up in Supreme Court of Canada.

 ??  ?? Monday: Premier John Horgan announces the project will go ahead.
Monday: Premier John Horgan announces the project will go ahead.

Newspapers in English

Newspapers from Canada