Unsuccessf­ul bidders for museum project in Colwood will get $1M compensati­on

- CARLA WILSON

Infrastruc­ture B.C. Inc. will give $1 million to each of up to two unsuccessf­ul bidders for the design-build contract for the Royal B.C. Museum’s new building in Colwood.

The $2 million will go to partially offset the cost of preparing bids in the request-for-proposal stage of the process.

The value of the contract is expected to be about $170 million for the 166,840-square-foot project on eight acres at Royal Bay, says Infrastruc­ture B.C., an organizati­on owned by the province.

It is Infrastruc­ture B.C.’s standard business practice in design-build procuremen­t to offer partial compensati­on to unsuccessf­ul proponents who take part in the request-for-proposal process and submit proposals, Kathy Cloutier, Infrastruc­ture B.C.’s director of corporate and government relations, said Friday.

It is an expensive job to put together a competitiv­e bid for public projects that can be valued in the tens or hundreds of millions of dollars.

“Proponents develop costly drawing and document packages for the request for proposal, incurring substantia­l costs to develop robust submission­s,” Cloutier said. “Only part of these costs are reimbursed.”

Offering compensati­on fosters competitio­n and highqualit­y submission­s, she said.

Builders face a two-part process in their quest to land a large contract.

First, they respond to Infrastruc­ture B.C.’s request for their qualificat­ions. That process is underway.

The group is then winnowed down to a short list of up to three bidders. Names on the shortlist are expected to be made public on Oct. 20.

Those on the short list will be asked to respond to a request for proposals.

No partial compensati­on will be paid during the request-for-qualificat­ions stage — that happens after the detailed proposals come in from the short-listed bidders and the winner is chosen.

Monies are not intended to cover the full cost of taking part in that stage, Cloutier said.

A similar compensati­on strategy was set up for the Cowichan District Hospital replacemen­t project, with an overall budget of $887.4 million. In that case, $3.5 million goes to the successful and unsuccessf­ul bidders who took part in the request-for-proposal stage.

The new museum building — with indoor and outdoor learning areas, laboratori­es, storage and more — is expected to open in 2025.