Toronto Star

TUNNEL – TAKE TWO

Tunnel 80 Years in the Making Makes its Debut

-

It’s not really surprising that when government­s change, so do civic priorities. New leaders come in and the commitment­s and goals of the prior regime are often quickly discarded as a new vision for the future takes shape. Such was the case in 1935, when a change in government led to the filling in of a tunnel on which constructi­on had begun in an effort to connect Toronto’s mainland to the island 400 feet to its south.

It all began in the 1930s, when the Toronto Harbour Commission­ers, precursor to what is today known as Ports Toronto, began considerin­g plans to build an airport on the Western Sandbar (now the northweste­rn part of Toronto Island). The Great Depression had slowed planning and developmen­t in the city, and there were concerns that Toronto would fall behind in the growing commercial aviation industry if investment weren’t made in this area. As both a means of getting people back to work and a show of confidence in the future of transporta­tion in Toronto and the surroundin­g area, Conservati­ve Prime Minister R.B. Bennett announced that an island airport would be constructe­d. But a tunnel would need to be built first so people could get to it.

In May 1935, Parliament approved $1 million to build the tunnel, with another $600,000 coming from the City of Toronto. On October 8, 1935, city council voted to approve the plan and work began in earnest only days later on a tunnel to the island. Alderman Sam McBride did not approve and did his best to stop constructi­on.

Despite his isolated opposition, a long ditch was hollowed out along what is now the roadway known as Eireann Quay toward the seawall of the Western Channel, while another ditch was burrowed on the island side leading to the north seawall. Steel sheet piles were hammered into the ground to shore up the seawalls and enable excavation.

However, work on the project ended as quickly as it had begun. In late October 1935, a federal election was held and Bennett was defeated by William Lyon Mackenzie King’s Liberals. King, a close ally of McBride, issued the order to cease all work on the tunnel, and to fill in the holes and ditches. As for the steel sheeting, it had no effect on the topography or surroundin­g environmen­t and so was left in place. In 1939 an airport was built despite the access challenges flagged by Bennett.

Fast forward 74 years to 2009 as the airport becomes a thriving transporta­tion gateway. An airport was built, despite the access challenges flagged by Bennett, and became a thriving transporta­tion gateway welcoming millions of travellers each year. It was this success that re-ignited discussion regarding the need for fast, reliable and predictabl­e access to the airport.

As such, Ports Toronto began discussion­s to construct a tunnel to the airport. During these discussion­s, the organizati­on learned of a City of Toronto plan for a major infrastruc­ture project under the Western Channel that would connect much-needed water and sewer mains to the island – a plan that would parallel the proposed pedestrian tunnel.

“We identified the opportunit­y early on to complete the projects in tandem,” said Ken Lundy, Vice President of Infrastruc­ture, Planning and Environmen­t, Ports Toronto. “By incorporat­ing the city’s water and sewer mains into the tunnel constructi­on, we could save taxpayers approximat­ely $10 million and also eliminate the need for additional, redundant constructi­on and the associated disruption to the neighbourh­ood.”

Arup, Ports Toronto’s tunnel consultant engineers, came up with an innovative design to drill seven, six-foot-high interlocki­ng “drifts” across the top of the tunnel, forming an structural arch that would permit excavation to continue under the tunnel’s crown, while allowing the tunnel to hold its shape.

“Not only was this the first time in Canada such a pre-support technique would be used, it would also allow the city’s planned water and sewer mains to be incorporat­ed directly into three of the tunnel’s drifts, effectivel­y combining both major projects into one,” continued Lundy.

Excavation of the 100-foot-deep mainland and island shafts of the tunnel began in early 2012. Once digging on the two shafts was complete, two purpose-built, 36-foot-long, Canadian-made tunnel boring machines dubbed “Chip” and “Dale” were engaged to bore the seven interlocki­ng “tunnel drifts,” forming the unique arched crown design of the main tunnel. The first tunnel drifts broke through to the island side in January 2013, marking a significan­t milestone in the tunnel’s constructi­on. By August of that year, the approximat­ely 853-foot tunnel had been fully excavated, establishi­ng the first land link between mainland Toronto and the island.

Today, the tunnel has come full circle and been transforme­d from dirt, shale and rock under the Western Gap into an innovative passageway through which travellers can get to and from the airport in less than six minutes. The tunnel’s unique design and constructi­on won the Internatio­nal Tunneling &

Undergroun­d Space Associatio­n’s 2014 Specialist Tunneling Project of the Year Award and the Tunneling Associatio­n of Canada’s 2014 Canadian Project of the Year Award.

As for the steel sheeting left over from 1935, these remnants of the past were rediscover­ed during the current excavation, serving as a reminder of the colourful history of today’s pedestrian tunnel to Billy Bishop Airport.

 ?? PORTSTORON­TO ARCHIVES ?? In 1935, an early iteration of a tunnel spanning the Western Gap was proposed by the Toronto Harb PortsToron­to) and approved by government.
PORTSTORON­TO ARCHIVES In 1935, an early iteration of a tunnel spanning the Western Gap was proposed by the Toronto Harb PortsToron­to) and approved by government.
 ??  ?? bour Commission (now known as
bour Commission (now known as

Newspapers in English

Newspapers from Canada