Toronto Star

Spadina subway extension could cost $400M more

- TESS KALINOWSKI TRANSPORTA­TION REPORTER

Toronto and York Region are facing an additional $400 million in constructi­on claims and other expenses on the overdue Spadina subway extension.

The costs would be split 60/40, with Toronto on the hook for $240 million and York Region $160 million for the 8.6-kilometre transit line.

The extension, from Downsview Station to the Vaughan Metropolit­an Centre near Hwy. 7, is about 85 per cent complete. Testing will begin in April 2017 for an opening later that year, about two years after the originally scheduled launch.

It is now tracking to cost $3.2 billion, up from the most recent $2.8-billion budget, according to a TTC staff report released Friday. CEO Andy Byford, who came to the TTC in 2012, has called the project “an albatross around my neck.” But on Friday, he expressed relief and pride that the end is in sight.

“At the end of 2017, when this railway opens, it will be spectacula­r. It will be something Toronto and York Region can be very proud of,” he said, following a media tour of constructi­on at the York University Station.

Byford would not say exactly how much of the additional $400 million — a figure reported by the Star last March — was for claims, since the TTC is still negotiatin­g with its six contractor­s.

He said he’s confident in the accuracy of the figure, which comes from a detailed analysis by Bechtel, the engineerin­g firm hired last year for $150 million to take over management of the project.

“Can I say with certainty that figure won’t change? No. It could come in less than $400 million. Certainly that is what we’re hoping to achieve. But because some of the claims will almost certainly go to litigation, I can’t predict the outcome,” he said.

It will be up to the city to figure out where the money comes from, but it will be accounted for in the capital budget. It will not affect fares, he stressed.

Virtually all major constructi­on projects have claims, where contractor­s try to recoup the costs of design changes, scope or materials. In many cases a settlement is negotiated. When that doesn’t work, the matter goes to litigation, which can take years. The Sheppard subway, which opened in 2002, still has an outstandin­g property claim.

But the Spadina subway has many claims related to changes to the complex station designs, which were modified and scaled back along the way.

“Ultimately if you cannot afford to build something that is architectu­r- ally spectacula­r, that should be built in at the start and not keep changing the designs,” Byford told reporters.

The York University station, which features a signature boomerangs­tyle roof built from curved steel, was the last site to be built and is the least complete, at only about 63 per cent.

But it is expected to be the busiest stop, accommodat­ing about 30,000 riders a day.

The subway was supposed to open in 2015, but a series of delays, including a late flow of federal funds, meant the work, originally scheduled to start in early 2007, didn’t get underway until late 2008. The schedule was never adjusted to account for that, said Byford.

If an outside project manager hadn’t done a reset, the subway probably would not have opened until late 2018 or even 2019, said Byford, who last year fired two senior TTC executives who had been in charge of the Spadina extension.

The city is reviewing the TTC’s capital program and considerin­g whether the transit agency should be in charge of large constructi­on projects.

The head of Infrastruc­ture Ontario, the province’s agency in charge of public-private partnershi­ps, including the Eglinton Crosstown LRT, said there are better ways to protect the public interest.

Bert Clark said TTC management appears to be handling the project with competence. But, “it inherited a series of constructi­on contracts that do not appear to provide the public sector owner with sufficient protection. You can’t undo that now,” he said.

Newspapers in English

Newspapers from Canada