Toronto Star

OPG must buck trend to deliver mega-project on time and on budget

- BRADY YAUCH Brady Yauch is the executive director and economist at the Consumer Policy Institute, a division of Energy Probe Research Foundation.

Ontario Power Generation (OPG), the provincial­ly owned power generator, believes it can do what almost no other company has been able to do: complete a mega-project on time and on budget.

The project in question is the refurbishm­ent of OPG’s 30-year-old Darlington nuclear plant. The mega-project is expected to cost the province’s ratepayers $12.8 billion, which according to the OPG’s applicatio­n before the Ontario Energy Board (OEB), leads to at least11-per-cent annual rate hikes for the next decade and billions of dollars of deferred costs that will burden future ratepayers for decades thereafter.

But the ramificati­ons from OPG’s nuclear project will be felt by mega-project supporters across the globe, as it will finally put to bed the question on whether mega-projects — even with nearly a decade of planning and billions of dollars of preparatio­n — can ever meet their financial and scheduled estimates.

It’s hard to quibble with OPG and its confidence in its most recent mega-project, given the mountain of evidence the company has submitted to the OEB for review.

Planning for the project is nearly a decade in the making, with OPG first examining refurbishm­ent and the economics of the project as far back as 2007. By 2010, the company began piecing together the complex engineerin­g plans and cost estimates needed to complete the refurbishm­ent.

By 2014, the company had already constructe­d a full-scale replica of one of the reactors — a planning exercise OPG says has never been done before and is touted as the primary reason that the refurbishm­ent’s schedule and cost estimate won’t go off the rails once it begins this month.

Over the past two years, the multiple engineerin­g companies and their thousands of contractor­s who will be working on the refurbishm­ent have been practising their work on the full-scale replica in an effort to make them more efficient and knowledgea­ble once they start dealing with a real reactor. Every single tool that will be used in the project has been purchased and tested. Nearly all of the materials for the project have also been purchased in an effort to avoid supply chain delays.

Late in 2015 — nearly five years after the company began piecing together its estimate for the final price tag of refurbishm­ent — it released a full estimate of what the project would cost. Like most mega-projects, because of the length of planning they entail, the economic environmen­t has changed since the Darlington refurbishm­ent was first discussed.

In Ontario, demand for power has continued to fall while the province continued to contract for more power, creating a massive surplus that it dumps into neighbouri­ng states and provinces at fire-sale prices. The price consumers pay for power has nearly doubled since then.

In total, OPG will have spent more than $2 billion in preparatio­n for the refurbishm­ent. The company has paid multiple consulting companies to review its plans, set up a number of internal review panels and even constructe­d new roads and highway off-ramps from the 401 in an effort to make it easier for the workers to get into and out of the constructi­on site. No corners have been cut in terms of preparatio­n.

The level of detail on the refurbishm­ent is overwhelmi­ng. OPG even set up “war room” exercises with some of the contractor­s involved to nail down the exact cost and the hours of work needed to get everything done on time and on budget.

OPG has done everything it can to avoid cost overruns because the company knows its track record with megaprojec­ts is dismal. The price tag for the company’s last mega-project — Niagara tunnel — was 50-per-cent higher than its original estimate. Its track record on previous nuclear projects is even worse. When the company refurbishe­d the Pickering units, the cost was triple the original estimate and two years behind schedule. Pickering remains one of the worst-performing reactors in North America.

OPG is not alone. Research from Bent Flyvbjerg out of Oxford University, one of the world’s leading experts on megaprojec­ts, shows that more than 90 per cent of all megaprojec­ts go over budget.

So let’s take this opportunit­y from OPG as an example for future megaprojec­ts: if this one can’t be done within its approved budget and schedule, it’s likely none of them can and we can end this charade once and for all. Taxpayers, who are often left footing the bill, will be better off.

 ??  ??

Newspapers in English

Newspapers from Canada