New LRV deal features higher late penalties

Contract with French transit maker contains fees for delays 35 times greater than with Bombardier

- BEN SPURR TRANSPORTA­TION REPORTER

The French company tapped to provide vehicles for new Toronto-area light rail lines will face major financial penalties if the cars are late, the Star has learned, which the province hopes will prevent the kind of messy legal dispute it’s found itself in with its original supplier, Bombardier.

Last month, Ontario Transporta­tion Minister Steven Del Duca announced the provincial government had reached a $528-million deal with Alstom for 61light rail vehicles (LRVs), 44 of which could end up in service on the Eglinton Crosstown.

Bombardier signed a deal in 2010 to supply the fleet for the Crosstown and other Toronto-area lines, but it has missed delivery deadlines, and, as the province’s dispute with the Quebecbase­d company dragged on, the government opted to place the order with Alstom as backup.

More than a month after Del Duca’s announceme­nt, the province has yet to release details of the Alstom contract, which it issued on a sole-source basis.

However, sources with knowledge of the deal confirmed that Alstom will pay a penalty of $55,000 a day for each vehicle that’s late. That’s more than 35 times greater than the late penalties in the Bombardier contract.

The contract with Alstom also caps the total late penalties the manufactur­er can incur at 13 per cent of the value of the contract, compared to the 5-per-cent cap in the Bombardier deal. While the Bombardier contract contained “subcaps” on damages that could make it difficult to recoup the full 5 per cent, the Alstom deal has no such subcaps.

In response to the Star’s questions, a spokespers­on for Del Duca said confidenti­ality provisions in the Alstom contract prevent the ministry from disclosing informatio­n that could be proprietar­y or commercial­ly sensitive.

But he said the contract contained “strengthen­ed” provisions that protect the public interest. “We expect all of our suppliers to honour their contractua­l obligation­s, perform profession­ally and to recognize that there are consequenc­es for failing to do so,” said Celso Pereira.

The weaker penalties in the Bombardier contract were a major factor cited by Metrolinx, the provincial transit agency, in its decision to move to cancel the deal l ast year. That’s because the late fees Bombardier would incur were dwarfed by the financial consequenc­es Metrolinx said it would face if the Crosstown’s 2021openin­g date was delayed.

In court documents filed earlier this year as part of the contract dispute, Metrolinx estimated that it would owe the consortium building the Crosstown up to $500,000 a day if the line’s opening was pushed back because the vehicles hadn’t arrived on time.

Bombardier, meanwhile, would only be on the hook for $1,500 a day for each late vehicle.

Metrolinx said the disparity between the penalties left it exposed to major financial risk.

Last fall, Metrolinx served Bombardier with a notice of intention to terminate the $770-million contract, which was for 182 cars, 76 of which were slated for the Crosstown. Metrolinx claimed the company had defaulted on the deal because, among other reasons, it hadn’t delivered the first two prototype vehicles on time.

In April, an Ontario Superior Court judge blocked Metrolinx from terminatin­g the contract for default, and, instead, ordered both parties to work through a dispute-resolution process. That process continues. Metrolinx is appealing the court ruling.

A spokespers­on for Bombardier said, in an email, the company is confident the dispute-resolution board will confirm that the manufactur­er has “complied with all of its obligation­s under its contract.”

“Bombardier is ready, able and willing to deliver all 182 vehicles to the people of Toronto on time,” MarcAndré Lefebvre wrote.

Under the terms of its deal, Alstom will supply 61 of its Citadis Spirit LRVs to Metrolinx. The company, which is also building vehicles for Ottawa’s LRT project, has pledged to open a manufactur­ing facility in the GTHA.

Seventeen of the vehicles will be used on the Finch West LRT, which is also scheduled to open in 2021. Should Bombardier make good on the order for the Crosstown fleet, Metrolinx will deploy the other 44 Alstom vehicles on the planned Hurontario line in Mississaug­a and Brampton.

 ??  ??
 ?? METROLINX/TWITTER ?? Alstom ageed to supply 61 of its light rail vehicles to Metrolinx.
METROLINX/TWITTER Alstom ageed to supply 61 of its light rail vehicles to Metrolinx.