Is the Scarboroug­h subway a good value for the money?

Cost comparison study will be up for debate at council Wednesday

- JENNIFER PAGLIARO CITY HALL BUREAU

Ontario PC Leader Patrick Brown, outgoing TTC CEO Andy Byford and transit activists sporting a “white elephant” costume and masks all had something in common this week.

All expressed support that council get a value-for-money analysis of the controvers­ial Scarboroug­h subway extension so it can be compared to the light-rail alternativ­e.

Whether to request that study will again be up for debate at council on Wednesday after it was deferred at a meeting last month.

“I think residents want council to be sure that they are providing as much transit to as many people as possible with every dollar that they’re entrusted with,” said Councillor Josh Matlow, who will move a motion that his colleagues direct the city’s auditor general to do that.

“And if council doesn’t have that basic relevant informatio­n, then they’re making decisions in the dark and that’s not responsibl­e nor acceptable.”

On Monday, both Brown and Byford told the CBC’s Matt Galloway they supported such a study.

“I support a value-for-money audit on every aspect, on everything the government spends taxpayer dollars on,” Brown said when asked specifical­ly about Scarboroug­h transit on Metro Morning.

In a separate interview, Byford said that he has “no objection” to that analysis being carried out.

“If council doesn’t have that basic relevant informatio­n then they’re making decisions in the dark.” JOSH MATLOW COUNCILLOR (WARD 22, ST. PAUL’S)

What is the subway plan? Council has endorsed a one-stop subway extension of the BloorDanfo­rth line that currently ends at Kennedy station to a new station adjacent to the Scarboroug­h Town Centre. It will replace the existing and aging six-stop Scarboroug­h RT that runs from Kennedy station to McCowan station.

Wait, I thought there were going to be three new stops? An earlier plan replaced the existing SRT with a three-stop subway from Kennedy station to Sheppard and McCowan Aves.

But last year, city staff presented a plan to build more transit, they said, within the $3.56-billion envelope of available funding. City staff said that by removing two subway stops, a 17to 18-stop LRT along Eglinton East could also be paid for. But as costs of the subway ballooned, that LRT line has been left largely unfunded. A cash-strapped city council would have to find hundreds of millions of dollars to pay for any additional subway stations.

What was the LRT plan? LRT stands for “light-rail transit,” which is different, more modern technology than what is currently used on the SRT line and what is used in many other North American and European cities. The city originally approved a seven-stop LRT in the same corridor as the SRT, separated from traffic, that would have run from Kennedy to Malvern at Sheppard Ave. and Markham Rd.

The plan had already been studied, was agreed to by the province and city and was just three months away from going out for contractor bids to do the constructi­on work when in October 2013, council, under former mayor Rob Ford, voted to scrap that plan in favour of a subway that was then estimated to cost $2 billion more.

How much does the current subway plan cost? Is that the final cost? The one-stop subway extension is currently estimated to cost $3.35 billion, but since that figure is based on very preliminar­y design work, it could climb by as much as 50 per cent, city staff say, putting the upper end estimate at just over $5 billion.

There are also significan­t and necessary costs not included in that figure, including the cost to finance constructi­on of a project of that size, city manager Peter Wallace told council in July 2016. The former chief financial officer said that financing could cost the city an additional $200 million for every $1 billion in project costs, or roughly $670 million for a $3.35-billion project.

What does the LRT plan cost? The province, according to a stillsigne­d master agreement, is committed to fund the entire project, which was estimated at $1.48 billion in 2010 dollars. Since then, the design of Kennedy station has changed to accommodat­e other connection­s and would require redesign.

Since staff stopped studying the LRT in 2013, that cost has not been estimated. Though a controvers­ial briefing note produced by the TTC put the updated cost of the LRT on par with a subway, a recent investigat­ion by the auditor general found that cost estimate could be off by at least $570 million.

Has council ever seen a comparison of those plans? No. That kind of study has never been requested by council and therefore never produced. Matlow moved a motion in March 2017 to request that study, but the motion lost 17-27. A buried draft report from the provincial transit agency Metrolinx found the subway was “not a worthwhile use of money” when compared to the LRT.

Can the city’s auditor general perform a value-for-money audit of the two options? Yes. The auditor general, Beverly Romeo-Beehler, in her recent investigat­ion, said she was considerin­g conducting such an analysis. She does not need council direction to do so. However, Romeo-Beehler later told the Star she has decided against doing such a study, saying it isn’t her role to reopen council decisions. Requesting the auditor general to add that study to her 2018 work plan, as Matlow will attempt to do, requires a two-thirds majority of council to pass, or 30 votes. Will I get where I’m going faster on the subway? Not necessaril­y. The one-stop subway extension would improve the time it currently takes to get from Scarboroug­h Centre to Kennedy station on the SRT by five minutes, according to city staff. When considerin­g the eliminatio­n of a transfer at Kennedy station, the time saved is eight minutes at most. But that time saving does not consider the extra time most Scarboroug­h residents will spend on the bus getting to the one new subway station or that residents, such as those in Malvern, would see their travel times cut in half by an LRT.

An analysis by Ryerson University found most transit users would spend on average of 6.8 minutes more on the bus to get to the subway stop compared to the closest LRT station, and 3.6 minutes longer than they do now to get to the existing SRT.

Won’t an LRT be crammed full of people? Isn’t a subway needed? Not according to city data. By 2031, the number of people expected to ride the subway in the busiest direction at the rush hour is 7,300 people. That is less than half the 15,000person capacity of an LRT and would leave subway trains, which have a 25,000-person capacity, at least 70 per cent empty at rush hour. The LRT was earlier projected to carry 8,000 people at rush hour in the busiest direction in 2031, well within an LRT’s capacity.

The one-stop subway extension is currently estimated to cost $3.35 billion, but could climb by as much as 50 per cent

Isn’t that still pretty busy for one stop? When you factor in that this will be the longest single gap between stops in the TTC’s entire system — 6.2 kilometres of tunnel — this subway stop does not rank anywhere near the busiest comparable stretches that exist today. While the extension would carry 64,000 passengers daily by 2031, the stretch between Museum and Bloor-Yonge stations sees station usage of 755,750. The Sheppard subway, which is almost six kilometres and has been considered to be a “white elephant” because it must be heavily subsidized by taxpayers to operate, has a daily ridership of 98,150.

How much would the LRT impact traffic? Not at all. The LRT replacemen­t for the SRT was planned to run in the same corridor, separated from all vehicular traffic.

I’ve heard LRTs don’t work well in the winter. So, isn’t it a bad idea to build an LRT in Toronto? “LRT is a proven technology that is used around the world including extremely cold places such as Edmonton, Minneapoli­s, Stockholm and Bergen,” a fact sheet from Metrolinx reads. The city is currently building a 19-kilometre LRT through the heart of midtown called the Eglinton Crosstown, and nine kilometres will run at street level.

Would I have to get off the LRT to transfer onto the Bloor-Danforth subway at Kennedy? Yes. An LRT means riders would still have to transfer at Kennedy, but the station was originally designed to significan­tly improve that transfer — just a single flight much like the transfers that already exist in the subway system such as at St. George, Bloor-Yonge and Sheppard-Yonge stations. That connection would have to be moved if council went back to the LRT. As part of a redesign of Kennedy station, it’s likely the LRT platform would be on the same level as the subway, requiring passengers to just walk across a platform.

But haven’t they already agreed to build a subway? Council still has to vote to approve constructi­on for a subway once staff provide a more accurate cost figure, which is now not expected until 2019. Though Mayor John Tory and others have pointed out the number of votes the subway has already faced, most were part of the regular approvals process and the others were the result of the subway being modified from a three-stop plan to today’s single-stop proposal under Tory’s administra­tion.