Toronto Star

Crosstown builders sue Metrolinx

LRT constructi­on consortium suing agency and demanding an extension for the project

- BEN SPURR

The constructi­on consortium building the $5.3-billion Eglinton Crosstown LRT is suing the regional transit agency and demanding an extension to the project’s scheduled completion date.

In a five-page notice of action filed with the Ontario Superior Court of Justice on Tuesday, Crosslinx claims it’s owed compensati­on because it has incurred damages and increased costs as a result of Metrolinx’s failure to live up to the project’s contract.

The notice doesn’t specify how much the consortium believes it’s owed.

Crosslinx is also seeking a declaratio­n from the court that it’s entitled to push back the Crosstown’s agreed-upon completion date.

The 19-kilometre line is currently supposed to enter service in 2021.

“I can confirm that we have filed a notice of action against Metrolinx for breach of contract,” said Kristin Jenkins, a spokespers­on for Crosslinx, which is a partnershi­p of constructi­on giants Aecon, Dragados Canada, EllisDon, and SNC-Lavalin.

Jenkins wouldn’t discuss specifics of the case, saying Crosslinx is “not talking about the dispute outside of the legal process.”

“We are focused on building the Crosstown and meeting our contractua­l obligation,” she said.

LAWSUIT continued on GT6

In an emailed statement, Metrolinx CEO Phil Verster said the agency “has been working closely with Crosslinx over several months on their alleged reasons for a claim,” and Metrolinx remains “committed to achieving the September 2021 opening date” for the line.

“As with any contract, claims are considered and reviewed thoroughly and we continue to work with Crosslinx to reach an outcome that fairly addresses the challenges that they have encountere­d,” Verster said.

The agency has not yet filed a statement of defence.

Crosslinx entered into a contract in 2015 to design, build, finance and maintain the Crosstown, which is believed to be the biggest infrastruc­ture project in the province’s history.

According to the notice of action, Crosslinx’s claim is based in part on allegation­s that work performed by utility companies exceeded timelines Metrolinx had guaranteed.

The document also cites “issues regarding permits, licences and approvals” and “delays” and “disruption­s” affecting the design approval process.

The notice claims that the events “were beyond the reasonable control” of Crosslinx.

 ?? RANDY RISLING/TORONTO STAR FILE PHOTO ?? Metrolinx says it remains “committed to achieving the September 2021 opening date” for the Eglinton Crosstown LRT.
RANDY RISLING/TORONTO STAR FILE PHOTO Metrolinx says it remains “committed to achieving the September 2021 opening date” for the Eglinton Crosstown LRT.

Newspapers in English

Newspapers from Canada