Toronto Star

Eglinton LRT lacks ‘credible plan’

Internal Metrolinx report calls consortium’s completion date ‘ambitious’

- LEX HARVEY TRANSPORTA­TION REPORTER

The consortium building the Eglinton Crosstown LRT says it expects the long-delayed transit project to be completed by March 2023, but the provincial transit agency overseeing the project says that date is “overly ambitious.”

In an internal Metrolinx performanc­e report from September obtained by the Star, Metrolinx said Crosslinx Transit Solutions does not have a “credible plan” to complete the LRT. It ascribed the “continuous slippage of the project’s plan” to the “underperfo­rmance” of Crosslinx.

The documents give a detailed picture of the ongoing strife between the provincial agencies overseeing the project, Metrolinx and Infrastruc­ture Ontario, and Crosslinx, the consortium made up of four constructi­on and engineerin­g companies.

Crosslinx and Infrastruc­ture Ontario did not respond to requests for comment by the Star. Metrolinx reiterated a statement it gave the Star in September, where it said it had expected the LRT to be up and running this fall, but Crosslinx fell behind schedule.

In its internal report, Metrolinx said the testing of the entire system is lagging behind schedule. “The plan’s projection is extremely ambitious and (Crosslinx) has continuous­ly failed to achieve the goals,” the documents read.

Constructi­on and engineerin­g work on the line are 98 per cent complete, the documents say, while testing is only 78.5 per cent done.

The report says the current approved budget is $12.82 billion, up from $12.24 billion in 2019. It also shows Crosslinx has more than $260 million in outstandin­g claims against Metrolinx and Infrastruc­ture Ontario.

The LRT has been under constructi­on since 2011 and was initially to be completed in 2020, but the timeline for the 19-kilometre light rail transit line has been pushed back several times, to the dismay of commuters and Eglinton businesses that have put up with more than a decade of heavy constructi­on.

According to the report, which was first reported by CBC News, Crosslinx now expects the LRT to be complete by March 2023, though Metrolinx casts doubt on the viability of this timeline, calling the testing schedule “overly ambitious and not achievable.”

Among a list of issues Metrolinx identified is “lack of a credible plan toward the completion of the project.” Crosslinx, Metrolinx alleges, has not laid out the requiremen­ts for achieving revenue service demonstrat­ion — the point at which the transit agency can begin running the trains along the line to test that there are no problems.

“This is critical to understand­ing the schedule and a realistic project completion date. Until this aspect can be agreed upon and a credible plan accepted, the schedule remain (sic) categorize­d as red in status.”

Metrolinx flags issues with the work Crosslinx has completed so far, “including but not limited to failure of waterproof­ing/water ingress leading to leakages and mold; and damaged public-exposed concrete.”

The transit agency also outlines ongoing safety concerns with Crosslinx. While the consortium has improved its safety measures since an LRT worker was hit and killed by a cement truck driver in May, the report outlines, the transit agency and Infrastruc­ture Ontario have continued to observe some violations of mobile equipment standards, which are important to preventing injury and death.

The relationsh­ip between Metrolinx and Crosslinx has been rocky for several years. In 2018, the provincial transit agency paid Crosslinx an extra $237 million to keep the project on track. But in February 2020, Metrolinx blamed the LRT’s delayed opening date on Crosslinx’s failure to meet constructi­on targets, plus defects in old infrastruc­ture under the TTC Eglinton station.

In December 2021, Metrolinx, Infrastruc­ture Ontario and Crosslinx struck a new deal on the cost and timeline for the transit line after a legal battle over who should be responsibl­e for the added costs to the LRT’s constructi­on imposed by the pandemic. Ultimately, an Ontario Superior Court Justice ruled in Crosslinx’s favour, and the province had to pay Crosslinx an extra $325 million for the project.

In December 2021, Metrolinx said the transit line would be complete by September 2022 and ready for service in 2023, but in September, the Star reported the line was delayed again.

The Metrolinx report flags issues with the work Crosslinx has completed so far, ‘including but not limited to failure of waterproof­ing/ water ingress leading to leakages and mold; and damaged publicexpo­sed concrete’

 ?? STEVE RUSSELL TORONTO STAR F I L E PHOTO ?? An internal Metrolinx performanc­e report from September details ongoing strife between the provincial agencies overseeing the Eglinton Crosstown LRT project and the consortium of constructi­on and engineerin­g companies.
STEVE RUSSELL TORONTO STAR F I L E PHOTO An internal Metrolinx performanc­e report from September details ongoing strife between the provincial agencies overseeing the Eglinton Crosstown LRT project and the consortium of constructi­on and engineerin­g companies.

Newspapers in English

Newspapers from Canada