Waste water treatment plant stirs controvers­y

$ 22.4- million project has residents grilling council over the facility’s technology and location

- DAPHNE BRAMHAM dbramham@vancouvers­un.com

They ( council members) think they are running a private corporatio­n rather than a public office.

JEF KEIGHLEY CONCERNED CITIZEN OPPOSED TO NEW SEWAGE PLANT

There’s a litany of trouble in the seaside paradise of Sechelt that involves a cast of colourful characters and has its genesis in — what else? — an election and a whole lot of money sloshing around in the community of 9,291.

It’s a story that raises questions about financial controls on municipal councils, transparen­cy, and the unintended consequenc­es of a flood of infrastruc­ture money from federal and provincial government­s. It also may portend a future of increased conflict between municipal leaders and taxpayers, a majority of whom will soon be retired and living on fixed incomes.

At the centre of the maelstrom is the largest infrastruc­ture project in Sechelt’s history: a $ 22.4- million waste water treatment plant.

But the story starts in November 2011, when John Henderson was elected mayor after spending nearly $ 16,200 — $ 10,731 from his own pocket — to secure the $ 35,000- a- year job.

His official biography tells of an entreprene­urial career in Vancouver and Hong Kong and features a photo of the flamboyant Henderson with his $ 120,000, electric- powered, orange, Tesla Roadster with Sechelt emblazoned on the side. Last October, the District of Sechelt’s office installed the first of 11 electric charging site on the Sunshine Coast.

A second charging site is planned for the district’s other office on Field Road.

So, compliment­s of Sechelt taxpayers, the B. C. government, Livesmart BC and the Fraser Basin Council, Henderson can charge his three- year- old Tesla free while he’s at work.

Henderson’s council includes the only two incumbents to survive a call for change led during the last municipal campaign by a group called For a Better Sechelt or FABS. Even though it didn’t specifical­ly endorse any candidates, FABS raised and spent about $ 46,200.

To put that in perspectiv­e, that’s 15 times more than the $ 3,000 cap on third- party spending in each riding during provincial election campaigns. Put another way, it is per- voter spending that in Vancouver would have amounted to third parties spending $ 1.8 million, or nearly six times the $ 312,263 that was spent.

Community in turmoil

It seems ever since the election, the community has been roiling. Six senior staff out of a total of 52 district employees have resigned or been fired. Among them are: two chief administra­tive officers ( the second lasted only six months), the chief financial officer, the corporate services director and the sustainabi­lity director. Henderson says he’s talked to other B. C. mayors and the turnover is “far from the highest.”

But local critics question the need for and the cost of the firings and the reason for the sudden resignatio­n of the chief financial officer. Because personnel matters are confidenti­al, there are no answers to that.

In its first year, council has already admitted to overspendi­ng the budget by nearly $ 1 million; a big chunk of that resulted from a decision to take over operation of a failed, private golf course.

The final numbers aren’t in yet, but Henderson admits the $ 1 million doesn’t include $ 160,000 spent on interim staff, nearly $ 500,000 in employees’ severance pay or $ 625,000 for paving three roads that later turned out not to be on land owned by the District of Sechelt.

But what’s got some people ready to revolt is the new sewage plant.

Sewage plant change

On Feb. 5, Henderson announced that a $ 22.4- million plant would be built downtown on the site of an existing plant, which is surrounded by homes and sits on a peat bog barely above sea- level on the aptly named Ebbtide Street.

Less than a year earlier — on April 12, 2012 — council had endorsed constructi­ng the new plant on Dusty Road, near the other plant. It is an industrial site between two gravel pits, which a previous council had purchased specifical­ly for an expanded waste water treatment plant. The Ebbtide site was to be sold for redevelopm­ent. A 2010 consultant’s report indicated the money from that sale would likely fund “a substantia­l portion of the new plant.”

Residents were also told council had chosen technology that is untried in any of the more than 30,000 sewage plants in North America.

All of the discussion­s and decisions made about the plant — choosing the builder, the site, the technology and even how to pay for it — were done privately at in camera meetings. And, by the time taxpayers got their first look at it, council had already signed a contract with the successful bidder and spent or committed more than $ 1 million.

Some Ebbtide Street homeowners, fed up with years of enduring the stink from the aging facility, were furious.

One of them, Betty Anne Pap, went to council in mid- March along with more than 100 other protesters demanding greater public consultati­on. Pap ended her presentati­on by asking whether the decision to rebuild on the Ebbtide site has anything to do with the fact that the mayor’s $ 1.16- million home is only a few hundred metres from the Dusty Road site.

Henderson was indignant when asked about the decision and whether where he lives had anything to do with it.

“I only have one vote out of seven on council,” he said in an interview, adding the downtown site was the unanimous choice of the successful bidder as well as the sewage facilities steering committee.

The sewage committee’s Dec. 18 meeting, at which the successful bidder’s proposal was discussed, was held in camera. Minutes from that meeting were not released to the public until March 6 and there is no indication how any of the members voted.

The minutes do note that before that meeting, there had been at least one project steering committee meeting and fullday workshops. Those meetings and workshops were also not open to the public. Aside from district staff, project steering committee members and two consultant­s who had been hired by council, the only others at the workshops were a representa­tive from the Sechelt First Nation and a representa­tive from the Coast Community Builders Associatio­n.

“As long as it’s noiseless, odourless and green, I don’t care where it goes,” Henderson said, adding his “adopted family” — his goddaughte­r and her parents, a Filipino couple who emigrated to Canada with the Hendersons’ help after having worked for them in Hong Kong — live right across from the Ebbtide plant.

“The project is going to be fantastic for the community, a win for everybody ... It’s right beside a duck pond and a marsh ( which is owned by the Nature Conservanc­y).”

Tourist attraction?

What council has agreed to build is essentiall­y a big greenhouse over top of sewage holding tanks. Sewage will be screened before it goes into the tanks, where microbes and plant roots will feed on the biomass. Once the treatment is completed, the sludge will be “de- watered” and treated. The water that comes out of the plant could be used for irrigation or even flushing toilets. But that’s not included in the $ 22.4- million price.

Henderson believes the sewage plant may become a tourist attraction. Already, he says, other mayors have expressed interest in having a look when it’s finished. And Henderson said it offers the potential for great business opportunit­ies.

Among the mayor’s highestpro­file critics are Jef Keighley, a former national director of the Canadian Autoworker­s Union and co- chair of the Sunshine Coast branch of the Council of Senior Citizens Organizati­on; and Barry Pruden, an emeritus professor at the University of Calgary’s chemical and petroleum engineerin­g school.

In a nine- page letter to Sechelt council dated Feb. 25, Keighley outlined the concerns of the seniors’ group: an opaque tendering process; the choice of the downtown location instead of an industrial site that council had endorsed less than a year ago; and, the cost.

“They ( council members) think they are running a private corporatio­n rather than a public office,” Keighley said in an interview. He calls Henderson “the NIMBY mayor.”

Henderson, in turn, says Keighley has no business intruding in Sechelt’s business since he lives outside the district in nearby Halfmoon Bay.

Pruden’s criticisms are technical ones, gleaned from a close reading of the documents in the request for proposals and from what he knows from his experience­s running waste water treatment plants and teaching engineerin­g students about how to design them.

His conclusion about the new plant? “It will be obsolete almost by the time it’s built.”

And it has nothing to do with the new technology. “I’m basically uni- dimensiona­l. They ( council) can do what they want about the technology.”

Pruden’s concern is that the engineers were given the wrong informatio­n by council in the request for proposal stage.

It all comes down to measuremen­ts and which ones were used in the specificat­ions for the new plant.

Costly expansion: critic

The request for expression­s of interest, dated January 2012 and sent out to engineerin­g firms for proposals, says the Dusty Road facility’s capacity is 2,200 cubic metres a day and Ebbtide’s capacity is 1,700 cubic metres daily for a total of 3,900 cubic metres.

But the replacemen­t plant will only have a capacity of 4,000 cubic metres. As Pruden says: “We’re only gaining 100 cubic metres of capacity a day for $ 22.4 million.”

And that’s Pruden’s best- case scenario.

When the district set the specificat­ions for the new plant, Pruden said it used the readings from the old meters instead of the newer, more sophistica­ted, Doppler ones installed a few years ago.

He believes the current capacity was under- estimated by as much as 50 per cent. Further, the retired engineerin­g professor believes that within a few years of the new plant’s scheduled completion in September 2014, Sechelt will need capacity for treating 5,500 cubic metres of sewage each day.

“My major concern is that I think they have done a lousy job of measuring the flow of grey water ( the sewage that goes into the plant). To me, the flow number is blatantly and absolutely incorrect.”

Finally, there’s the question of cost and how it will be paid.

Because of a confidenti­ality agreement with the other four bidders, it’s not known whether the cost of the chosen design is in line with the others. Henderson said in an interview that the greenhouse technology is more expensive than traditiona­l treatment methods, but he declined to say how much more.

Pruden looked at a recent, published study of constructi­on costs of 126 sewage treatment plants across North America. Based on that, Pruden says the cost of the Sechelt plant is 20 per cent higher than the most expensive one in that study.

So far, Sechelt has only secured half the funding – $ 8 million from the federal gas tax fund, which is administer­ed by the Union of B. C. Municipali­ties and the province, and $ 3.2 million from the Building Canada Fund.

The rest will come from: a projected surplus of $ 4.5 million in the sewer operating fund at the end of 2013; $ 2.39 million from general operating surplus and reserves; and $ 2.5 million in short- term borrowing, which doesn’t require taxpayers’ approval.

The mayor hopes the Sechelt First Nation will invest $ 1.6 million, but no agreement has yet been reached. Since the plant’s completion date isn’t until September 2014, Henderson says there’s still time for Sechelt time to find other sources of funding.

Despite the protests at council and letters to the editor of the local newspaper, the mayor rejects suggestion­s that Sechelt residents are anything less than happy with council or his leadership.

He points to a survey of 300 residents done by Innovative Research Group at a cost of $ 16,500 that found two- thirds were happy with the services they received.

But that survey was taken three months before residents were told the sewage plant would remain downtown and four months before council released 168 pages of documents ( including the request for proposals and plant specificat­ions) from in camera meetings dating as far back as March 2012.

So, what’s really going on in Sechelt? Did council choose the right technology and the right contractor and get it all at the right price? Is the biggest infrastruc­ture project in the district’s history the best ever? Or is it the worst ever?

Those are the $ 22.4- million questions.

 ??  ?? An artist’s rendering of the proposed Sechelt sewage treatment plant illustrate­s the plan to build what is essentiall­y a greenhouse over the sewage holding tanks.
An artist’s rendering of the proposed Sechelt sewage treatment plant illustrate­s the plan to build what is essentiall­y a greenhouse over the sewage holding tanks.
 ??  ?? Sechelt Mayor John Henderson drives an electric- powered Tesla sports car.
Sechelt Mayor John Henderson drives an electric- powered Tesla sports car.
 ?? VANCOUVER SUN/ GOOGLE MAPS ?? After resolving to build its new waste water treatment plant near the Dusty Road facility, council reversed its decision and will instead build on the current site of the Ebbtide plant.
VANCOUVER SUN/ GOOGLE MAPS After resolving to build its new waste water treatment plant near the Dusty Road facility, council reversed its decision and will instead build on the current site of the Ebbtide plant.