Vancouver Sun

Pipeline work set to start in September

Kinder Morgan unveils plans despite ongoing debate on project

- GORDON HOEKSTRA

Kinder Morgan’s schedule for the $7.4-billion Trans Mountain oil pipeline expansion shows constructi­on work is to start as early as Sept. 1.

The detailed schedule was filed recently with the National Energy Board, one of 157 conditions that must be met for the company based in Houston, Texas to begin constructi­on.

It shows the large scope of the project where land-clearing on some portions of the 1,150-kilometre pipeline route will begin in September.

Pipeline constructi­on will start as early as October in Alberta, with boring of a tunnel through Burnaby Mountain scheduled to start in March 2018.

The first detailed look at how constructi­on is to unfold shows the company is gearing up to start constructi­on in less than three months, even though there continues to be legal and political fights to stop the project over concerns of an oil spill and increased oilsands emissions.

Kinder Morgan declined an interview Thursday on its constructi­on plans and scheduling — and any delays they may face.

In a written statement, Kinder Morgan’s Trans Mountain spokeswoma­n, Lizette Parsons Bell, said people should expect constructi­on will take place according to the schedule.

“However, the schedule is subject to refinement as we work through detailed engineerin­g, design and constructi­on planning and meeting conditions,” she said.

The project would twin the existing pipeline and nearly triple capacity to 890,000 barrels a day, providing a conduit for bitumen from the Alberta oilsands to the coast and opening new markets in Asia.

The project has federal and provincial regulatory approval, and the backing of Prime Minister Justin Trudeau, but there are more than a dozen legal challenges by First Nations, municipali­ties and environmen­tal groups that have yet to be heard.

An NDP-Green alliance is expected to take power in B.C. within a month, with both NDP Leader John Horgan and Green Leader Andrew Weaver saying they will do everything in their power to stop the project.

That includes possibly joining the legal challenges from First Nations, and potentiall­y denying provincial permits, such as those needed for logging along the route.

Hilary Novik, an analyst at the political risk consultanc­y firm Eurasia Group, said political developmen­ts in B.C. are being watched carefully, including any uptick in intensity of protests. She cited a recent event where activists chained and locked themselves to a fence outside Kinder Morgan’s Westridge terminal in Burnaby.

She said her company is also watching to see whether Trudeau will continue to back the project should “massive” protests materializ­e, as they did in North Dakota against the $3.7-billion Dakota Access oil pipeline.

“We do think he will stand by his approval,” said Novik, based in Washington, D.C.

She said that’s because Trudeau has already invested too much political capital not to see the project built.

Another potential headache for Kinder Morgan is more than 400 statements of opposition, an unusually large number, filed with the NEB on the detailed route.

The NEB will determine which of those are valid — some certainly will be ruled invalid — and a panel will be set up this fall to hear arguments from the company

and landowners and others who believe the pipeline route has a direct effect on them and should be changed.

If the NEB panel decides the route should be changed in some areas, the company would need to re-do planning work for a new route, say NEB officials.

Ian Stephen, a campaign director for the Chilliwack-based Waterwealt­h Project, filed an opposition letter — although he does not own land directly on the route.

Stephen is among those in Chilliwack who believe the twinning of the pipeline is a risk, if there is a spill, to important wetlands and to the aquifer that supplies drinking water in the area. Changing the route outside the aquifer, and moving the existing pipe outside the aquifer, would solve the problem, he said.

 ?? PAUL B. CONNOR/KINDER MORGAN ?? Constructi­on work on the Kinder Morgan Trans Mountain Pipeline is planned to begin this fall, with materials delivered in September and welding beginning in October.
PAUL B. CONNOR/KINDER MORGAN Constructi­on work on the Kinder Morgan Trans Mountain Pipeline is planned to begin this fall, with materials delivered in September and welding beginning in October.

Newspapers in English

Newspapers from Canada