Vancouver Sun

B.C. HYDRO’S SITE C PROMISES RING HOLLOW

Uncensored report shows project eating through contingenc­y funds

- VAUGHN PALMER vpalmer@postmedia.com

B.C. Hydro was nine per cent over budget and already dipping into contingenc­y funds from Day 1 on the main constructi­on contract at Site C, according to the uncensored version of a report to the B.C. Utilities Commission.

The troubles continue to the present day, with the $1.8-billion main civil works contract having run through three-quarters of its contingenc­y budget with only one quarter of the work being done.

Those and other disturbing details are contained in a report from Deloitte LLP, the consulting firm hired to scrutinize Hydro’s numbers as part of the cabinet-ordered review of the Site C dam project.

The commission released the Deloitte report on its website Sept. 8, then took it down because it neglected to black out passages that were supposed to be kept secret. Later it was reposted with those details obscured.

There matters stood until I was chatting this week with Robert McCullough, the U.S.-based energy expert who has been working here for the anti-Site C Peace Valley Land Owners Associatio­n. He advised me that he had an unredacted version of the Deloitte report posted to mresearch.com.

There, British Columbians can see budget figures and other details B.C. Hydro and the commission sought to withhold about the contract for civil engineerin­g works at Site C — covering excavation of the two riverbanks and constructi­on of diversion tunnels, coffer dams and the giant earthworks dam itself.

Hydro budgeted that part of the project at $1.559 billion when the B.C. Liberals green-lighted constructi­on in December 2014.

The following year, the estimate was boosted to $1.612 billion.

Neverthele­ss, all four bids came in well above. The lowest was $1.748 billion from Peace River Hydro Partners, a consortium made up of Spain’s Acciona Infrastruc­ture, South Korea’s Samsung, and Alberta-based Petrowest Corporatio­n.

Even going with the low bid, Hydro had to draw $136 million from contingenc­ies to close the funding gap, a detail that was somehow left out of the Dec. 22, 2015 press release announcing the contract.

The target date for start of constructi­on was Jan. 21, 2016. But the partners were two months late in getting going and remained behind schedule into the summer.

Hydro had to intervene, and with a further $33.5-million dip into contingenc­ies, managed to get things back on track by January of this year. A month later, a 400-metre-long tension crack opened up on the north bank, forcing a 10-week delay in constructi­on. That was barely under control when a second crack, 250 metres long, opened up on the same bank in mid-May.

By the time Deloitte began asking questions in late August, Hydro was still dealing with the contractor­s on the budgetary and scheduling fallout from the two cracks and other problems.

While Hydro was reluctant to share details, Deloitte did learn that on Aug. 24, the partners filed a claim for an additional $327-million payment and a 435-day delay in their share of the constructi­on schedule. The latter would mean missing the September 2019 target for diverting the river, putting the whole project behind by a year.

Hydro rejects both claims and Deloitte concluded that the partners probably underbid by several hundred millions and are now trying to make it up.

But that still leaves the challenge of the schedule.

“The partners’ ability to meet critical milestones poses a major challenge to the project,” Deloitte wrote.

Plus, one of the partners, Petrowest, has gone bankrupt, a developmen­t that “will create a period of instabilit­y that may impact the (contractor­s’) ability to meet its planned work schedule in the short to medium term.”

Nor did the consultant­s let Hydro off the hook.

The low bid on the main civil works contract came in 12 per cent higher than Hydro’s initial estimate, 8.5 per cent over the utility’s final number.

“Which raises concerns about Hydro’s ability to estimate large contracts,” Deloitte concluded.

The immediate consequenc­e can be seen in the report’s uncensored numbers on contingenc­ies.

Just two years into an eight-year schedule, the main civil works contract has already eaten 77 per cent — $194 million — of its $252-million share of the contingenc­y budget, leaving 23 per cent to cover all remaining overruns.

The proportion­s are reversed on work completed — 24 per cent — versus what remains to be done — 76 per cent.

Not surprising­ly, the consultant­s expect Hydro will have to raid other parts of the contingenc­y budget to cover further overruns with the main civil works contract before long.

Deloitte then goes on to note B.C. Hydro’s record on this contract “reduces our confidence in the accuracy of the other main contract packages that have yet to be awarded.”

Next up is the second-largest contract on the project, for building the generating station and main spillway. Budgeted at $1.255 billion, but in the absence of access to the bids, Deloitte rightly wonders if that’s a take-it-tothe-bank estimate.

Still to come is a contract for transmissi­on lines to link Site C to the provincial grid. Another redacted passage in the report discloses that the transmissi­on lines have already incurred additional costs of $494 million.

Hydro continues to insist it can hit the mark on both the Site C budget and the river diversion.

But those claims ring hollow, given the facts on display in the uncensored version of the Deloitte report.

The partners’ ability to meet critical milestones poses a major challenge to the project.

DELOITTE LLP REPORT ON SITE C PROJECT

 ?? B.C. HYDRO ?? This photo taken in July shows constructi­on work progress on the B.C. Hydro Site C dam project on the Peace River.
B.C. HYDRO This photo taken in July shows constructi­on work progress on the B.C. Hydro Site C dam project on the Peace River.
 ??  ??

Newspapers in English

Newspapers from Canada