Vancouver Sun

TRANS MOUNTAIN EXPANSION PROCESS INCHING FORWARD

Detailed route hearings to focus on landowners’ concerns over pipeline

- GORDON KENT gkent@postmedia.com twitter.com/GKentYEG

The expansion of Kinder Morgan Canada’s Trans Mountain pipeline was approved by the federal government in 2016, but the $7.4-billion project continues to run into roadblocks.

Although the Alberta ban on B.C. wine is grabbing headlines, the controvers­ial pipeline expansion still must complete a complex regulatory process before the whole enterprise can go ahead.

While court decisions or political calculatio­ns could throw off the timetable, here’s an overview of the major steps on the way to a green light.

Q What’s the National Energy Board doing now?

A The 1,147-kilometre pipeline twinning has been approved within an approximat­ely 150-metre-wide corridor, but now the independen­t federal agency must determine exactly where in that corridor the pipe will be installed.

Detailed route hearings across Alberta and British Columbia will handle local concerns by landowners and intervener­s about the timetable, location or method of building the pipeline.

There are about 60 active hearings.

The board has heard all the issues raised regarding the line between Edmonton and the Jasper National Park gate, and released the first written decisions this week.

Detailed hearings for most of the B.C. route will be held from late February to early May in Valemount, Clearwater, Burnaby, Kamloops and Merritt, but the schedule for a segment near the Lower Mainland won’t be released for one or two months.

Q How much has been done so far?

A The vast majority of landowners didn’t file objections, and the energy board says more than half the entire detailed route has been approved. The board doesn’t determine what people will be paid to have a pipeline run through their property. If necessary, the minister of Natural Resources can appoint an arbitrator.

Q Now what?

A These are the last public hearings on the pipeline. However, Kinder Morgan must fulfil 157 conditions imposed by the energy board before all its obligation­s are met, although many don’t need to be satisfied before constructi­on starts.

The company provided thousands of specific commitment­s to the energy board about how the project will be constructe­d or operated which it’s required to track.

In addition, it must obtain federal, provincial and municipal permits covering road crossings, fisheries, environmen­tal protection, access to Crown land, building approval and many other issues. A status table shows 19 have been completed and 39 are in progress.

After Kinder Morgan complained last year that Burnaby was taking too long to provide permits, the energy board ruled it could ignore the city’s bylaws and start constructi­on in the area.

Q What does the future hold?

A The company expects to invest $1.8 billion on the expansion this year, including working on Burnaby’s Westridge Marine Terminal, obtaining permits, and doing detailed engineerin­g and design.

It also has also met the energy board’s conditions allowing it to set up temporary infrastruc­ture sites as far west as the B.C. Interior for purposes such as pipe storage, contractor yards and camps.

However, Kinder Morgan has indicated all the delays mean the pipeline won’t be in service until December 2020, a year later than originally planned, and it won’t commit to full constructi­on spending until there’s more progress on permits and it’s clear the project can be completed.

 ?? FRANCIS GEORGIAN ?? A drill rig gathers informatio­n on ground conditions for the routing of Kinder Morgan’s Trans Mountain pipeline expansion in Coquitlam. A 150-metre-wide corridor has been approved for the project, but the exact route is still the subject of hearings.
FRANCIS GEORGIAN A drill rig gathers informatio­n on ground conditions for the routing of Kinder Morgan’s Trans Mountain pipeline expansion in Coquitlam. A 150-metre-wide corridor has been approved for the project, but the exact route is still the subject of hearings.

Newspapers in English

Newspapers from Canada