Vancouver Sun

NDP’S UNION PACT HELPS FUEL HIGHWAY PROJECT OVERRUNS

- VAUGHN PALMER Victoria Vpalmer@postmedia.com Twitter.com/VaughnPalm­er

The New Democrats admitted to a major budget overrun on a big-ticket highway project Thursday, while minimizing the added cost of one of their union-favouring community benefit agreements.

Transporta­tion Minister Claire Trevena claimed the CBA added a mere 5.8 per cent to the cost of four-laning an onerous stretch of the Trans-Canada Highway through Kicking Horse Canyon.

But to get an accurate perspectiv­e on the impact of NDP policy on the budget, one had to look back to a disclosure statement posted on her ministry website a little more than two years ago.

The statement, filed under provincial budget legislatio­n, put the cost of four-laning a nearly-five-kilometre stretch of highway, through the canyon, at an already hefty $450 million.

It went on to acknowledg­e some “primary risks” to the project budget including changes because of “cost escalation, stakeholde­r feedback, geotechnic­al and environmen­tal issues, traffic management during constructi­on and archaeolog­ical issues.”

But the statement, signed by the project manager on March 17, 2017, also said that “the project scope, schedule and budget have been developed with considerat­ion for the above risks and probabilit­y of occurrence.”

Despite those assurances, the ministry announced Thursday the projected cost had overshot the two-year-old estimate by almost a third. The $450 million has now become $601 million.

The escalation was attributed in part to interest during constructi­on of $23 million, a factor that inexplicab­ly was not included in the original estimate.

Plus there was $39 million in additional funding for things that supposedly were incorporat­ed in the earlier estimate, including cost of materials, geotechnic­al concerns, and engineerin­g and design changes. Also, there was $6 million for additional archeologi­cal work, consultati­ons with First Nations and technical resources.

The ministry added $48 million to the contingenc­y budget “to reflect the risk and complexity of the project.” How big was the contingenc­y allowance in the 2017 budget, where all those identified risks were supposedly taken into account? The ministry refused to say.

Then came $35 million as the imputed cost of the community benefit agreement, to cover NDP-imposed standards for hiring, training, living accommodat­ions, pensions and other benefits and working conditions. The New Democrats derived their lowball estimate of 5.8 per cent by comparing the $35 million to the revised project budget of $601 million.

But the claim did not stand up to scrutiny based on another budget considerat­ion that was addressed back in the 2017 statement.

Because this project entails rebuilding the Trans-Canada Highway, the budget is cost shared between the federal and provincial government­s.

But Ottawa shrewdly capped its contributi­on at $215 million, leaving B.C. to pick up the balance, plus 100 per cent of any overruns. Thus, B.C.’s share has gone from $235 million before the overruns to $385 million after, an increase of two-thirds. The CBA added nine per cent to the provincial share, not the just-under six per cent claimed by the New Democrats.

If one deducts the cost of interest during constructi­on — which was there all along whether or not the province admitted it — then the added costs to the provincial share amount to $128 million under the NDP. By that reckoning, the CBA contribute­d 27 per cent of the provincial­ly driven overrun.

The briefing materials for Thursday’s presentati­on shed some additional light on the impacts of the CBA, which has been cloaked in secrecy since the New Democrats set the policy in motion. Wages and benefits account for only about a third of the $35 million.

There’s also a $15-million provision for living accommodat­ions, meaning a state-of-the-art work camp for the isolated site.

Lastly, the breakdown included $8 million spread over four years to cover operationa­l costs for B.C. Infrastruc­ture Benefits, the Crown corporatio­n establishe­d by the New Democrats to administer the community benefit agreements.

The BCIB is now up and running with a staff of 32 and an annual budget of $8 million. The agency claimed in a briefing document that great strides are being made in recruiting under-represente­d groups to the constructi­on workforce, including local hires, apprentice­s, women and Indigenous people.

The first of the community benefit agreement projects, launched earlier this year, is the widening of a two-kilometre stretch of the Trans-Canada along the Illecillew­aet River east of Revelstoke.

“We’re operationa­l,” the agency boasted, in claiming that 11 of the 15 people working on the project were from “one or more approved hiring categories.”

That project has gone over budget under the NDP as well. Announced at $63 million in February of this year, it grew to $85 million when the contract was awarded in May, again with the province on the hook for the entire overrun.

I wondered how much of the $22 million could be attributed to the community benefits agreement. But the ministry declined to say, perhaps realizing that the price tag might seem disproport­ionate when contrasted to BCIB having recruited a mere 11 hires in the preferred categories.

Meanwhile it should be noted that Thursday’s announceme­nt on the Kicking Horse Canyon stretch was a call for qualified bidders — not awarding the contract, never mind the start of constructi­on.

All that is slated to happen next summer, by which time who knows what additional budgetary surprises may emerge.

 ??  ??

Newspapers in English

Newspapers from Canada