Shanghai Daily

Game, set and match for Wang’s retractabl­e roof

-

EVEN today, the magnolia-shaped roof of the Qizhong Tennis Center’s center court remains a sophistica­ted structure that can hardly be duplicated, said Wang Qiyu, former deputy general manager of the tennis center in southwest Minhang District.

Wang, who used to work for Shanghai Sports Bureau, was in charge of the Qizhong Tennis Center project when the city government decided to build an arena capable of hosting internatio­nal tennis tournament­s such as the ATP Masters at the beginning of the century when tennis was still regarded as a “sport for the nobility” by most Chinese.

From 2002, when a constructi­on committee for the center was establishe­d, Wang has witnessed the building of a world-class arena as well as its extension and renovation, making sure it would serve the ATP tournament well.

He is still in charge of the daily maintenanc­e of the roof despite reaching retirement age last year.

“This is undoubtedl­y the best project of my career,” Wang told Shanghai Daily. He majored in mechanical automation in school and took part in the design and constructi­on of almost all the major sports venues in Shanghai, including Shanghai Stadium, the Oriental Sports Center and the profession­al football stadium in Pudong which is under constructi­on.

After Shanghai successful­ly hosted the Heineken Open from 1998 to 2001, it won the opportunit­y to host the ATP Finals, also known as the Masters Cup, in 2002.

“However, the Masters Cup requires an indoor arena, while the Xianxia Tennis Center where the Heineken Open was held didn’t have a roof,” said Wang. “The 2002 Masters Cup was therefore held in a temporary arena we set up in the newly built Shanghai New Internatio­nal Expo Center in Pudong. The city government then decided to build a new tennis court which can host both outdoor and indoor competitio­ns.”

Wang was among the first batch of staff to start work at Qizhong, which was still a rural area in early 2003.

“The major problem was, no design institute or architectu­re company in the country had experience in combining a constructi­on with a huge but sophistica­ted mechanical device.”

Wang said he knew about the difficulty when Shanghai Customs College attempted to build a retractabl­e roof for its swimming pool. However, the roof could not be opened on the very first day of its completion.

“At that time, Japan was a leading country in the area of retractabl­e roofs. We called for bids and decided to use a proposal by a Japanese design institute. The project was too complicate­d and Japan’s Mitsubishi Heavy Industries was the only constructo­r claiming it was capable of making the system. However, the company was asking for 300 million yuan (US$44 million).”

While Wang hesitated over the bid, a new candidate emerged — the People’s Liberation Army General Armaments Department’s engineerin­g design and research center.

“They make launchers for rockets and missiles. They are reliable because they are from the army. And most importantl­y, they quoted a price of just 1.2 million yuan,” said Wang.

The steel roof with eight sliding petal-shaped sections was eventually accomplish­ed around Chinese New Year of 2005. With a total weight of 280 tons, each sliding piece was of the size of four basketball courts. After tests on the ground, it was hoisted into place on top of center court.

“There was other work such as the choice of the covering material. We also had to make sure that the roof didn’t leak or all our efforts would be a waste,” said Wang.

On October 3, 2005, Roger Federer and then Vice Mayor Yang Xiaodu pressed the “open” button of the steel roof at a launch ceremony for the 15,000-seat center court — one month before the start of the 2005 Masters Cup.

Apart from the center court, Qizhong Tennis Center has six indoor courts and 16 outdoor courts.

Newspapers in English

Newspapers from China