Fiji Sun

First Harbor Builds Ironsands Port, Now Focuses on Other Possible Projects

- MARAIA VULA SUVA

The First Harbor Consultant­s Co., Ltd Fiji Branch is now focusing on major infrastruc­ture projects in Fiji and the region.

This follows its successful completion of the investment intensive Amex Resources Limited Mba Delta Ironsands Project at the Port of Lautoka. The Lautoka based Chinese company is currently one of the region’s most experience­d and the largest profession­al companies in harbor engineerin­g and sea port constructi­on.

Donald Singh, Stakeholde­r Manager, in an interview said they were looking forward to being provided a fair opportunit­y to participat­e in planning, design and constructi­on of infrastruc­ture projects in Fiji. “Collaborat­ions in the shape of Private Public Partnershi­p (PPP) or Build Operate Transfer (BOT) could also be considered by the company’s investment arm.”

Prior to the commenceme­nt of the Mba Delta Ironsands Project, FHC had carried out seawall constructi­on work at Kiuva Village.

The role of FHC Fiji Branch so far has been to carry out constructi­on, civil engineerin­g and architectu­ral design.

“Our broader scope covers transporta­tion, petrochemi­cal, electric power, architectu­re, public works and hydraulic works.”

The Mba Delta Ironsands project extensivel­y involved all aspects of civil engineerin­g, marine engineerin­g and constructi­on.

Mr Singh said: “During the Mba Delta Ironsands project constructi­on period several local companies have benefitted from the project in terms of supply of materials. “Local reinforcem­ent steel suppliers and concrete mix suppliers saw unpreceden­ted volumes of orders from this project.

“Heavy machinery including excavators, compaction equipment, rollers, cranes, hiab trucks, dumper trucks, loaders, forklifts and other assorted equipment were hired from local suppliers for earthworks and a few companies were also subcontrac­ted for steel and concrete fabricatio­n works.

“Local testing institutio­ns were engaged throughout the project period for high quality results.

“The company is proud to have worked with them and looks forward to maintainin­g healthy business relationsh­ips with such businesses even after the completion of this project, hopefully to be engaged again on our next undertakin­g in Fiji.

“Over the overall constructi­on period, around 400 personnel have been employed on the project. However, this number was spread across the various stages and at varying times depending on the need at each stage of constructi­on. “Currently, we have seven local staff still with the company to continue running the company, without any other current project, largely for future projects.”

Mr Singh said a significan­t number of personnel were brought in from China as they possessed required skill and expertise. “Projects of this magnitude often require technician­s and profession­als.

The company acknowledg­es and appreciate­s the prompt facilitati­on of work permits for incoming workers by the Fiji Immigratio­n Department.”

Relationsh­ip with AMEX

FHC has enjoyed a largely sound relationsh­ip with Amex Resources Ltd outside of the more formal Employer-Contractor contractua­l relationsh­ip.

“Working on this project, which is unique to Fiji, has been a challengin­g experience and also a vital learning curve as we worked hard to overcome constraint­s to achieve targets.

“We acknowledg­e the assistance and facilitati­on on many aspects from Amex, especially when dealing with local authoritie­s like the Lautoka City Council.”

Mr Singh highlighte­d: AMEX project

■Co■structio■ process, time tak

en to finish the AMEX project

■The time taken to build and complete this project was about three years.

■This project was an Engineerin­g, Procuremen­t & Constructi­on (EPC) project.

■The design specificat­ions were given by Amex which underwent revision and optimisati­on before the constructi­on commenced. Earthworks began in May 2017 whereby the topmost layer of soil was removed and new material was filled and compacted.

■The■, pile driving commenced. This was an enormous task due to the underlying geological conditions which made piling difficult.

■After that, the Storage Shed foundation was laid followed by the steel structure and cladding.

■Mea■whi●e, pile driving for the wharf berth wall began and this was also a difficult task also due to the underlying conditions.

■O■ce the King Piles and Sheet Piles were driven to design elevation, the constructi­on of the concrete Berth Wall began.

■Vast amounts of steel was sourced locally and expert workers completed steel-fixing work before

pouring of concrete for the Berth Wall and Wharf Pavement.

■The Filtration Plant was installed along with the conveyor belts leading from the Filtration Plant to the Storage Shed, and from the Storage Shed to the Shiploader.

■The Administra­tion Building, Workshop, Workshop Ablution Building, Laboratory and Control Room Building, Guardhouse, Workshop & Stores Building, Lunch Shed Building and Training Facility formed part of the Port Site layout.

■A●● this was constructe­d by FHC. Site surface constructi­on works involved excavation of the old top layer of soil and backfill and compaction with aggregate as per design specificat­ions.

■A●● electrical works have been compliant with Energy Fiji Limited’s standards and fully passed by EFL.

■However, the Port Site was not connected to the EFL grid as Amex would use generators for their operations.

■Five generator sets were supplied, installed and commission­ed by FHC.

■A●● constructi­on, both on land

and over waters were carried out in full compliance with environmen­tal protection laws and project works fully abided by the approved and adopted Environmen­t Management Plan, approved by Amex.

COVID-19

COVID-19 did affect the company’s operations to some extent.

“Most of our management and technical staff had returned to China for the Chinese New Year holidays and then due to COVID-19 travel restrictio­ns they were unable to return to Fiji.

“Some major works on Site were subsequent­ly delayed and we had to reorganise works with the available team.

“FHC did not lay off any local staff despite the lockdown being in force, and we actually fully implemente­d the ‘work from home’ idea.”

Investment­s, future operations

Moving forward, Mr Singh said FHC was keen on exploring opportunit­ies in port developmen­t, infrastruc­ture including roads, bridges, terminals, communicat­ion infrastruc­ture, etc.

“The company’s investment arm in China could even look at prospects where we could collaborat­e or partner with local developers or even the Fijian Government and actually consider investing in projects.

“Infrastruc­ture developmen­t is any country’s most vital pathway to growth and prosperity.

“We would definitely like to be part of Fiji’s growth and developmen­t.

“So it is vital that we begin seeking new challenges and begin talking to important stakeholde­rs. “Investing in Fiji is certainly in the company’s plans and the investment arm in China is fully supportive of this.”

 ??  ?? From left: Staff of First Harbor Consultant­s Co., Ltd Fiji Branch, Unayz Asum, Faruk Abdul, Asenaca Raikoti, Zhang Yekai, Zhang Zhong Xiao, Temesia Tanidrala, Ao Lei, Shi Xuetong, Ryan Hatch, Donald Singh, Atelina Kaloucava
From left: Staff of First Harbor Consultant­s Co., Ltd Fiji Branch, Unayz Asum, Faruk Abdul, Asenaca Raikoti, Zhang Yekai, Zhang Zhong Xiao, Temesia Tanidrala, Ao Lei, Shi Xuetong, Ryan Hatch, Donald Singh, Atelina Kaloucava
 ??  ?? An aerial view of the Amex Resources Limited’s Mba Delta Ironsands Project facility at the Port of Lautoka.
An aerial view of the Amex Resources Limited’s Mba Delta Ironsands Project facility at the Port of Lautoka.

Newspapers in English

Newspapers from Fiji