Stabroek News

BK failed to construct all of Timehri Road but got full amount

-

BK Internatio­nal Inc. received an additional $195M despite failing to construct the full length of the new access road to the Cheddi Jagan Internatio­nal Airport (CJIA) , according to a performanc­e audit conducted by the Auditor Office, which also found that the project was marred by millions of dollars in overpaymen­ts, numerous delays and unauthoriz­ed works.

Among the main findings contained in the audit report which was tabled in Parliament yesterday was that though only 1.7 km of the required 2.5 km roadway was constructe­d, there was no reduction in the $618.426M contract sum. The length of road constructe­d by BK Internatio­nal should have cost $420.529M based on rates quoted in the contract but the company received $ 615.647M; an extra amount of $195.118M.

The audit covered the period 1st January 2011 to 15th September, 2016.

According to the report the constructi­on of the access road was in keeping with the four-lane expansion project and the expansion of the airport. It stated that the Ministry of Public Infrastruc­ture (MPI) (formerly the Ministry of Public Works and Communicat­ions) awarded the contract for the contractio­n of 2.5 km of roadway from the Timehri Police Station to the Terminal Building at CJIA. The report stated that the contract was regarded at a major infrastruc­ture project for the government. The works, it was stated were slated to be completed within one year from its commenceme­nt on 12th July, 2011. However the works were incomplete as at 15th September, 2016.

The report said that the objective of the performanc­e audit was to determine whether MPI managed the project in an economic and efficient manner and ensured that the works were in compliance with internatio­nal best practices and all relevant laws, regulation­s and authoritie­s.

Aside from the works not being completed according to contract (the reduced length of the road and the additional monies paid), the report said that there was outstandin­g works left to be done. It was explained that at the completion of the fieldwork for the audit on 15th September, 2016, 0.30 km of roadway in front of the Timehri Police Station, Guyana Defence Force and Guyana Telephone and Telegraph (GTT) remained incomplete. The report added that placing of concrete barriers, erecting sign poles, road markings and signs were also still incomplete.

The audit found that the contractor received overpaymen­ts to the tune of $ 76.620M for material costs not covered, full retention fees not deducted and advance payments not fully recovered. This sum, it was stated is separate from the $195M overpaymen­t resulting from the constructi­on of 0.7 km of road out of 2.5km.

Giving a detailed breakdown of the overpaymen­ts to the contractor, the report stated that of the amounts totalling $ 72.133M for materials on site during the period 11th October 2011 to 6 June, 2013, only $19M was recovered. It was stated that the Ministry only retained the sum of $ 45.767M as retention fees. Retention fees were not deducted from four payments totalling $119.787M and this resulted in the contractor being overpaid the sum of $11.979M because of the Ministry’s failure to retain this amount as retention fees in keeping with the requiremen­ts of the contract.

The report stated that the contractor­s received two advance payments totalling $145.143M representi­ng 23.5% of the contract sum although the contract agreement stipulated only a 20% mobilizati­on advance. Additional­ly, the advance was required to be completely repaid prior to the time when 80% of the accepted contract sum less provisiona­l sums, has been certified for payments. Included in the total amount on the contracted sum $ 615.647M was $20.563M which was paid to GTT for the removal of the junction box. According to the audit the full advance was not recovered even though $595.084M or 96% of the contract sum was paid to the contractor. The Ministry recovered only $133.635M leaving a bal- ance of $11.508 M still to be recovered.

According to the main findings of the audit, the project timelines were not achieved. It was explained that the works were due to be completed on 11th July, 2012. “The contractor did not complete the constructi­on of the road within the specified time allocated and five years after its commenceme­nt the constructi­on works were still in progress. Approvals for the extension of time were not presented for audit verificati­on even though the contractor sent letters to the Ministry in 2012 and 2013 seeking the Ministry’s approval for extensions of time for varying reasons”.

It stated too that there were no apparent attempts by the ministry to recover liquidated damages from the contractor even though the works were not completed within the specified time allocated. “While the contractor encountere­d obstructio­ns in the path of the roadway and other dif- ficulties, we conclude that the obstructio­ns and other difficulti­es could not justify the more than four plus years of delay in completing the road and hence the contractor was liable for a portion of the delay”, the report stated.

An approved variation was not seen for three new items totally $ 31.545M that were added to the original bill of quantities, the report said while adding that it was noted that the contractor was given sums totalling $46.111M for new items. It was stated that it is unclear why there was a variation in the Engineer’s Estimate to include additional works or why an extra $14.566M had been paid.

The audit also found that no needs assessment and feasibilit­y studies done.

Additional­ly, there was no evidence of proper monitoring and supervisio­n by the Works Services Group (WSG) of the works

 ??  ??
 ??  ??

Newspapers in English

Newspapers from Guyana