Major breaches were seen in
Planning Authority dated February 24th, 2023, for the upgrading of roads in Block 3, Great Diamond.
The summary of findings said that Tepui itself submitted as part of its tender, a letter addressed to the NDIA and dated June 13th, 2023, under the hand of “Winston Martindale, Director” captioned “Record of Past Work Experience” in which it is stated – “Our company was registered in August 2022 and has now commenced the process of bidding for projects, hence we do not have any past work experience but our team of personnel have years of experience under upgrading and rehabilitation of roads as indicated on their respective resumes.”
The NPTAB said in part that the “construction of a pump station and a pile bed foundation involve multifaceted tasks and material supplies to create robust infrastructure. Commonalities lie in foundational aspects, with earthworks for the pump station and pre-stressed concrete piles for the wharf providing stability. Structural works are vital in both projects, encompassing the construction of pile caps and beams for the pump station and various structural elements like deck slabs and U-beams for the wharf. Additionally, revetment works are necessary for both to prevent erosion and ensure long-term stability. Both projects require meticulous attention to detail in supplying and installing essential components such as steel frameworks and pumps. Furthermore, aspects like road access, internal landscaping, and electrical works contribute to the functionality and aesthetics of both structures”.
Additionally, NPTAB said it acted on precedence and discretion to evaluation criterion No. 8, please see examples below.