POSCO PROJECT TIMELINE
2005
JUN 22: Posco signs MoU with Odisha govt to set up a 12 million tonne greenfield steel plant near Paradip at $12 billion AUG: Posco Pratirodh Sangram Samiti (PPSS) formed
2008
AUG 8: SC upholds “in principle” clearance for use of forestland for the project
2009
DEC 29: The environment ministry grants final clearance for diversion of forest land
2010
JUL 14: Odisha HC cancels grant of prospecting licence to Posco for Khadadhar iron ore mines OCT 29: Odisha govt moves the Supreme Court against the HC order
2011
JAN 31: MoEF gives conditional environment clearance to the Posco project
2012
MAR 30: NGT suspends the environment clearance granted to Posco
2013
MAY: Odisha announces acquisition of 2,700 acres to enable the company start work MAY 10: SC strikes down the HC order
2014
NOV: Odisha govt sends proposal for notified area of the proposed mining lease after the Centre asks it to clearly demarcate the notified and non-notified areas in the lease
2015
JAN 12: Centre promulgates MMDR Amendment Ordinance, 2015, which prescribes allotment of mining lease on auction basis