K-G Basin row: Slapping $1.55-bn notice was the easy part

- SAYAN GHOSAL

There has been much comment over the $1.55 billion demand made by the petroleum ministry on Reliance Industries (RIL) and its partners, BP and Niko Resources, for alleged unfair enrichment through gas migration from an adjoining Oil and Natural Gas Corporatio­n (ONGC) block in the KrishnaGod­avari (KG) basin.

The reports of large amounts of gas seeping into RIL’s block for over seven years led to the matter reaching the doors of the high court here. It constitute­d a one-person committee of A P Shah, who'd retired after being chief justice here, to investigat­e. His report, delivered on August 28, 2016, opened a Pandora’s Box of complexiti­es.

It confirmed the movement of gas into the RIL block and made a subsequent determinat­ion of unjust benefit to RIL (and its partners) due to extraction and retention of the resource, in contravent­ion to their production sharing contract (PSC) with the government. Its other important conclusion was that the migrated gas, as a national resource, belonged to the government and not ONGC. This got the petroleum ministry instantly involved in the quickly developing issue.

The government directed a technical arm to determine the amount of seeped gas extracted by RIL; it arrived at 338.332 million British thermal units. The ministry then calculated a dollar figure on the ‘unjust benefit’ made by RIL, leading to the $1.55bn notice on November 3, 2016.

RIL denied knowingly producing any gas from the ONGC block. It had, it said, always drilled on its own block, with prior approval of the government. As the liability demanded by the latter came under the PSC, Reliance invoked an arbitratio­n clause in the agreement for settlement of disputes, and served the government a notice on November 11. To roil the waters further, the company termed the demand an unpreceden­ted move in any oil and gas sector worldwide and demanded this be settled through internatio­nal petroleum industry practices, in line with the PSC.

What now?

In what seems to have all the makings of a Vodafone-like tussle, with the tax department trying to secure its demand without regard to arbitral proceeding­s, currently underway, all eyes are on how the government decides to handle this. According to Tejas Karia, partner, Shardul Amarchand Mangaldas & Co, this case is a bit different from the Vodafone one, which had involved a statutory liability as in the law of the land.

“In the present scenario, a mere demand has been made by the government, which is yet to be adjudicate­d in an arbitral forum,” he says.

Nonetheles­s, with all claims of such a high value, attempts by the government at securing the amount at the earliest are sure to be watched closely by the company and the legal community. Under the Arbitratio­n and Conciliati­on Act, there are several routes that may be taken to realise a demand even before conclusion of an arbitral process, if so chosen. Section 17 of the Act allows a party asserting a claim to approach the arbitral tribunal to secure the amount as demanded or to preserve the subject matter of the dispute, as an interim measure. However, as the arbitral tribunal in the present dispute is yet to be fully constitute­d, this provision cannot come to the aid of the government as of yet.

Possibilit­ies

Section 9 of the Act also allows an Indian court to provide similar relief at the interim stage. This provision may be invoked even before the constituti­on of an arbitral tribunal, right till the enforcemen­t of the eventual award.

“Such reliefs, however (by a court or tribunal, once constitute­d), must take into considerat­ion factors such as the financial strength of the company, potential for removal of assets, etc. In this case, it will be a tough hurdle for the government to obtain this kind of remedy, considerin­g the strong balance sheet of the company,” says Sitesh Mukherjee, partner, Trilegal.

Still, given the right circumstan­ces, if the government approaches the Indian court under Section 9, interim relief may be granted and this could be transferre­d to the arbitral tribunal once it is functional. “But, in case the petition for interim relief is finally disposed by the time the arbitratio­n tribunal is constitute­d, any relief provided would ordinarily continue throughout the arbitral proceeding­s, subject to appeal under the Act," notes Karia.

Once the arbitral tribunal is finally functional, though, any Section 9 action seems unlikely. For, the courts in India will not ordinarily entertain a petition for interim relief unless it is felt the tribunal cannot provide the necessary remedy on its own.

The issue has the potential of becoming even more complex, with RIL suing the government for damages if the arbitratio­n eventually turns in their favour. However the tale unfolds, there seems to be much gas left in the chamber.

 ??  ??