Business Standard

Without gas, 24k-Mw power units to go off the grid

- SHREYA JAI

Even as the country braces for a harsh summer, 24,000 Mw of gas-based power projects would go off the grid, owing to no supply of fuel.

These units belong to the state-owned NTPC and the Gujarat State Electricit­y Supply Company, as well as private players such as CLP India, Torrent Power, GVK Industries, and Lanco Power GMR Energy.

The central government was supporting the projects through a subsidised gas-bidding programme, but has now decided to shelve it. This follows reluctance from the states that have refused to purchase power at ~4 per unit.

“Gujarat, Andhra Pradesh, and Maharashtr­a, which have gas-based power projects, have refused to buy power from these plants, citing high costs. After the last round of bidding last year, states did not sign power-purchase agreements,” said a senior power ministry official.

Piyush Goyal, minister of state with independen­t charge for coal, power, mines, and new and renewable energy, was also reported to have said, “The scheme is being discontinu­ed. But, if there is interest from all sides, we can resume it.”

Of the 24,150 Mw of gas grid-connected power generation capacity in the country, 14,305 Mw has no supply of domestic gas. Investment in these projects, to the tune of about ~60,000 crore, could become non-performing assets.

The remaining capacity (9,845 Mw), with investment of about ~40,000 crore, is working at sub-optimal levels, because of the limited domestic supply of gas.

The government floated a reverse e-auction process for power plants to avail subsidy for buying costly imported gas — regasified liquefied natural gas (RLNG). This involved a reverse bid for the subsidy amount to come from Power System Developmen­t Fund (PSDF) to purchase RLNG.

The bid amount reflects the amount of subsidy support that the power generators seek from the government. The bidding was held on the e-bidding platform built by public sector undertakin­g the MSTC.

The eligible bidders indicated the total incrementa­l electricit­y they would generate using the e-bid RLNG. The companies also quoted the subsidy they required to ensure the net purchase price for the distributi­on companies to buy that power, without exceeding the target power load factor.

The four rounds were held in June 2015, and March, May and September last year.

Under a unique arrangemen­t, every stakeholde­r in the supply chain would have to forego a part of their returns on operations. While the central government would give up service tax it levies on gas sourcing, power plant operators would forego return on equity.

GAIL would source the imported gas, and, along with Gujarat State Petronet, would forgo 50 per cent of their transmissi­on rate and 75 per cent of marketing margin in supplying imported RLNG.

The lead banker to these plants would ensure all receipts of money would be utilised only for payments towards the variable cost of generation (fuel cost) and the operation and maintenanc­e expenses, in accordance with regulatory guidelines. Debt servicing would be made after capping fixed cost.