Business Standard

Bourses, top executives to pay for technical glitches

Penalty of ~1 lakh a day for delay in filing root cause analysis

- SAMIE MODAK Mumbai, 5 July

The Securities and Exchange Board of India (Sebi) on Monday issued a detailed framework for penalising market infrastruc­ture institutio­ns (MIIS), which include stock exchanges, clearing corporatio­ns, and depositori­es, for technical glitches.

“MIIS are systemical­ly important institutio­ns as they provide infrastruc­ture necessary for the smooth and uninterrup­ted functionin­g of the securities market…. for any downtime or unavailabi­lity of services, beyond such predefined time, there is a need to ensure that a ‘financial disincenti­ve’ is paid by MIIS as well as their managing directors (MDS) and chief technology officers (CTOS),” the market regulator said in a circular. Sebi said the move would encourage MIIS to constantly monitor the performanc­e and efficiency of their systems and upgrade them. This would avoid any possibilit­y of technical glitches, disruption­s, or disasters, and help them restart their operations expeditiou­sly in the event of any such incident, it added.

Under the new framework, MIIS will have to pay ~1 lakh per day in case of a delay in submission or incomplete submission of their root cause analysis (RCA). The regulator has said a comprehens­ive RCA report needs to be submitted within 21 days of the incident.

Failure to timely address the technical glitch will attract ~2 lakh per day for the first 15 working days, ~3 lakh per day for subsequent 15 working days, and ~25 lakh additional beyond that. The new rules come into effect from August 16. Failure to declare disaster within stipulated timelines can attract a financial disincenti­ve of 10 per cent of average standalone net profit for the previous two financial years or ~2 crore, whichever is higher.

The MII’S MD and CTO will have to part with 10 per cent of their annual pay (both fixed and variable components) for the financial year when the disaster occurred.

Failure to restore operations within a recovery time objective may attract similar penalties both on the MII as well as the MD and CTO. In the event of a disaster, the MII has to restore its operations, including critical systems, from a disaster recovery site within 45 minutes.

There will be further penalties for failing to restore operations of critical systems, including from disaster recovery site, within three hours.

Sebi has said that in the event of any business disruption, which is not required to be declared as a “disaster”, if the MII fails to restore normalcy of operations within 75 minutes of the incident, it will attract a penalty of ~50 lakh, and if the same extends beyond three hours, the penalty will rise to ~1 crore.

Newspapers in English

Newspapers from India