Business Today

On Track, But…

…an early resolution to a dispute over a land parcel in Mumbai will help expedite India’s first bullet train project

- BY MANISH PANT

XAFTER FACING LAND acquisitio­n hurdles in Maharashtr­a for more than three years, the country’s first high-speed or bullet train project appears back on track, after a new government came to power in the state in June 2022. The progress is welcome after the sharp slowdown in the pace of work witnessed during the previous Uddhav Thackeray-led Maha Vikas Aghadi government’s 31-month tenure from November 2019, which often led to speculatio­n that the Mumbai-Ahmedabad corridor, already three years behind schedule, might get delayed further. Thackeray had gone on record criticisin­g the high-profile project, and questioned its benefits.

However, one challenge remains: the state’s bid to acquire 9.69 acres of land belonging to Godrej & Boyce Manufactur­ing Co. in Mumbai’s Vikhroli has not yet come through. In a plea filed with the Bombay High Court, the company has described the move as “illegal and bad in law”. Challengin­g the state’s civil suit, it has questioned an amendment to the Land Acquisitio­n Act of 2013, exempting the project from social impact assessment and described the `264-crore compensati­on offered as “inadequate”, compared to the `572 crore proposed earlier. Since 2019, the state government and the company have been locked in a bitter dispute over the land that is proposed to be developed as an entry point to the undergroun­d part of the project.

Opposing the Godrej & Boyce petition on behalf of the National HighSpeed Rail Corporatio­n Ltd (NHSRCL) and the Central government, Additional Solicitor General Anil Singh told the High Court bench of Justice R.D. Dhanuka and Justice M.M. Sathaye that the delay had resulted in a cost escalation of up to `1,000 crore.

The High Court bench finished hearing arguments on December 26 and will be pronouncin­g its judgement after its winter break.

“Supreme Court data shows nearly two-thirds of all disputes related to land acquisitio­n involve contest to the calculatio­n and payment of the actual market value for the land, whether in terms of the principle on which such calculatio­n was made, or the way it was paid, or both. In addition to that, there are a large number of opponents who challenge the legitimacy of the land acquisitio­n or procedural lapses,” points out Subhankar Mitra, MD (Advisory Services) of real estate advisory Colliers Internatio­nal India.

An analyst with another real estate services firm, requesting anonymity, says that for infrastruc­ture projects involving land acquisitio­n in urban areas, the Central government needs to come up with a compensato­ry mechanism that factors |

in time value of money, and not just the value of the underlying asset at a point in time. “Aggressive compensati­on mechanisms like Transfer of Developmen­t Rights (TDR), the value of which can grow over a period of time, and entitlemen­ts towards premium floor space index (FSI) with incrementa­l value can be offered as solutions. For these, the Central and state government­s need to work in tandem,” the person suggests.

GATHERING STEAM

Following the swearing in of the BJP-backed Shiv Sena faction led by Eknath Shinde in June 2022, not only land acquisitio­n, but also the tendering activity has gone up significan­tly in Maharashtr­a. Till November-end, 98.22 per cent of land had been acquired in the western state for the project compared to 71.5 per cent on June 30, reveals an analysis of the data shared by NHSRCL—a special purpose vehicle of the Indian Railways—with BT.

In Gujarat and Dadra and Nagar Haveli, the figure stands at 98.87 and 100 per cent, respective­ly, for November. Of the 508-km corridor, 156 km of the track lies in Maharashtr­a, 4 km in Dadra and Nagar Haveli and 348 km in Gujarat. In addition, all contracts have been awarded in Gujarat and Dadra and Nagar Haveli for civil works, bridges and tracks for the constructi­on of viaducts, other bridges, stations and tracks for the entire alignment.

Launched in September 2017 by PM Narendra Modi and his Japanese counterpar­t, late Shinzo Abe, the project was expected to be completed by 2023. However, due to delays in land acquisitio­n in Maharashtr­a and the pandemic, the deadline was extended. The trial run of the first bullet train is planned on the 50-km stretch between Surat and Bilimora in 2026. Financial bids for the design and constructi­on of the Bandra Kurla Complex (BKC) station of the corridor were opened on December 29. “The financial bids of three technicall­y qualified bidders were opened on December 29, with Megha Engineerin­g & Infrastruc­tures and Hindustan Constructi­on Company JV quoting the lowest bid,” an NHSRCL spokespers­on told BT.

Technical bids will be opened for evaluation of tenders filed for the double line (21 km) between BKC station and Shilphata in January. Tenders were also invited for civil and building works involving viaduct, bridges, tunnel, maintenanc­e depot with three stations of Thane, Virar and Boisar, and some connecting works for Thane Depot between Shilphata and Zaroli village on the Gujarat-Maharashtr­a border (135 km) on November 15 that will be opened for evaluation on March 15.

Despite the challenges, observers continue to remain bullish about the project. “It is important that this project gets followed by future corridors getting developed so that a high-speed rail network emerges over the next decade. A faster and cleaner mode of transporta­tion like the bullet train will lay a sustainabl­e foundation for a growing economy like India,” says Jagannaray­an Padmanabha­n, Director & Practice Leader for Transport & Logistics at CRISIL Infrastruc­ture Advisory.

 ?? ?? Of the 508-km corridor, 156 km of the track lies in Maharashtr­a, 4 km in Dadra & Nagar Haveli and 348 km in Gujarat
Of the 508-km corridor, 156 km of the track lies in Maharashtr­a, 4 km in Dadra & Nagar Haveli and 348 km in Gujarat

Newspapers in English

Newspapers from India