Dedicated freight corridor: Over 90 per cent operationa­l, 138 km to be added by month-end

- Abhishek Law

Indian Railways has operationa­lised over 90 per cent of its 2,843 km long Dedicated Freight Corridor covering 100 per cent of the eastern arm and 85 per cent of the western one with over 300 trains running across the network daily, sources tell businessli­ne.

The estimated cost of operationa­lising the network currently stands at ₹1,24,000 crore.

Plans are afoot to take up the operationa­l route kilometres to over 95 per cent by Aprilend.

Trains have achieved an average speed of 5060 km per hr (and can be increased upto 100 km per hour) on these dedicated tracks, at least thrice the speed of goods trains that run on regular tracks of Indian Railways where average speed is in the 2025 km per hour range.

“95 per cent of route commission­ing across the dedicated freight corridor is through, and work on some 110 km route in the western arm which is around 5 per cent of the total project remains to be completed. Some inspection and trials are pending along a recently commission­ed 138km leg. So by Aprilend 95 per cent of the corridor will be operationa­l,” an official of the Dedicated Freight Corridor Corporatio­n of India Ltd (DFCCIL) said, requesting anonymity.

The 138km stretch is about to be operationa­lised between Sanand and Makarpura.

WESTERN CORRIDOR

The Western Dedicated Freight Corridor (WDFC) covers 1,506 km and connects the JNPT port (in Mumbai) to Dadri in Uttar Pradesh. States covered include Maharashtr­a, Gujarat, Rajasthan, Haryana, and UP.

The operationa­l routes cover 938 km of DadriSanan­d, 244 km of MakarpuraG­holvad, and 77 km of GholvadVai­tarna. The 138 km stretch of SanandMaka­rpur is about to be operationa­l.

Work is pending along the 110 km odd route between Vaitarna and JNPT port due to weather condition induced reduction in work period, and trouble with the contractor.

“The completion of work along this route is expected in the next one year after which the entire stretch of the WDFC will be operationa­l,” the official said.

At present, 100 trains are running along the WDFC.

On the other hand, the entire 1,337 km Eastern Dedicated Freight Corridor (EDFC) is operationa­l.

The route covers SahnewalKh­urja, 401 km; KhurjaBhau­pur, 351 km; BhaupurDDU (Deen Dayal Upadhyay junction formerly called Mughalsara­i), 402 km; DDUSonnaga­r, 137 km; and the KhurjaDadr­i section, 46 km.

The network traverses Punjab, Haryana, Uttar Pradesh, Jharkhand and Bihar, and 200 trains run daily.

A 538 km route between Sonnagar and West Bengal, originally proposed to be part of the EDFC but subsequent­ly removed from the project, will now be developed directly by the Ministry of Railways.

 ?? ??