Transmissi­on, last mile connectivi­ty remains a challenge

- RICHA MISHRA

In May 2014, when Piyush Goyal took over as Minister of State (Independen­t Charge) of Ministries of Power, Coal and New & Renewable Energy, he had said that one of his major priorities is to de-bottleneck the system and ensure fast delivery.

But as luck would have it, soon after he assumed o™ce he found himself dealing with Northern grid failure, which was mainly due to poor infrastruc­ture — weak transmissi­on network.

Since then, successive power ministers have continued with the reform process in the power sector. Measures have been taken to correct the situation and average availabili­ty of power has increased to 22.5 hours in rural areas and to 23.8 hours in urban areas, according to government data.

AT&C losses in power sector have come down due to reforms in revamped distributi­on sector scheme to help distributi­on utilities (Discoms) improve their operationa­l e™ciencies and financial sustainabi­lity.

One of the key contributo­rs to the Modi-led NDA getting a second term was promises of rural electrific­ation and subsequent­ly the promise of electricit­y in every household.

According to the Power Ministry, in the 10-year NDA reign, from a power deficient situation we are now in a power self-su™cient state, thanks to the substantia­l generation capacity added. Substantia­l transmissi­on capacity has also been added, it said.

Earlier this year, RK Singh, Minister of Power and New & Renewable Energy, had said that the power sector in India rewards its customers, adding that the government was racing to add electricit­y capacity to meet the growing demand.

Singh had further said that “we are the only country to have brought in general network access…” Singh had also claimed that he has tried to insulate the system and to curb the practice of making electricit­y a part of political parties’ freebies.

But critics would say that is easier said than done. During election time, promises are made across sectors.

LAST MILE ISSUES

The challenge that remains for any government in this sector is the last mile connectivi­ty — that is to ensure a healthy sub transmissi­on and distributi­on network which can flow power from producer to distributo­r to the consumer with ease.

According to Power Ministry statement of January 2024, during 2023, 14,390 ckm of transmissi­on lines, 61,591 MVA of transforma­tion capacity and 4,290 MW Inter-regional Transfer

Capacity have been added.

In the last nine years, with the addition of 1,87,849 ckm (64.48 per cent increase), the transmissi­on network of 4,79,185 ckm has evolved as the largest national synchronou­s grid in the world.

The total inter-regional capacity to transfer power from one region to another has been enhanced to 1,16,540 MW (224.17 per cent increase) from 35,950 MW in the last nine years. But herein lies the challenge. India has huge ambitions in energy transition and plans to have 500 GW of non-fossil based electricit­y installed capacity by 2030.

RENEWABLE PLANS

The Ministry of Power had constitute­d a high level committee under the Chairperso­n, Central Electricit­y Authority with representa­tives from Solar Energy Corporatio­n of India, Central Transmissi­on Utility of India Ltd, Power Grid Corporatio­n of India Ltd, Grid-India, National Institute of Solar Energy, and National Institute of

 ?? ??