Road widening yet to finish after 4 yrs

-

The Greater Hyderabad Municipal Corporatio­n (GHMC) is taking more than four-and-a-half years to complete the four lane road under the railway bridge at East Anandbagh, Malkajgiri. Residents complain that since then the road is closed, it is causing great inconvenie­nce to the colony people. They also stated that even after minister K. Taraka Rama Rao gave word in April, when he came to inaugurate a nearby constructi­on, that he would soon look into the issue, work has hardly commenced. Colony associatio­ns have sent repeated appeals through mails regarding the work.

Mr Ramalinges­wara Rao, a resident of East Anandbagh, said, “The much-awaited constructi­on started very recently, but it hasn’t moved any further than digging up of roads and that too was filled up in the recent rains.” The major festival of the colony, Vinayaka Chavithi, is about to begin, and residents are worried about how the situation would be in these half dug roads works.

Mr Suresh Kumar, general secretary, Anand Bagh Residents Welfare Associatio­n, stated, “Our colony road has been closed for this RuB. From then on, traffic has become very slow for the past four years due to closure of roads. School children, citizens and women are finding it difficult to cross the road. Business has also come to halt due to this. And recently a mechanic injured himself

The condition of road is bad since it is more than four years old.

Minister K.T. Rama Rao had assured in April that he would look into the issue.

Colony associatio­ns now demand for speeding up of the work.

while trying to use this road and the vehicle also got damaged. Nothing substantia­l has been done regarding this problem on the ground.”

The colony associatio­n members say that all the four department­s are involved in the workElectr­icity, Water Works, Roads and Buildings and GHMC, of which, Water Works has done the most irresponsi­ble job. “We don't know why the roads have been removed and re-carpeted so many times for the pipeline work. It’s better if all the department­s sit together, coordinate and work properly.” they said.

When contacted, Mr. N Raghu Prasad, Zonal Commission­er, said, “The road work is now being handled by the Railways and the work is slow as one needs to be careful with the railway track. It will speed up eventually.”

A GHMC official also mentioned that now they were working on a new improved plan for the project and the work would finish within two years as the funds had also been allocated for the same.

 ??  ?? Works for widening of the road near the railway bridge at East Anandbagh in Malkajgiri.
Works for widening of the road near the railway bridge at East Anandbagh in Malkajgiri.