Deccan Chronicle

HMDA in row over ORR toll contract

- MADDY DEEKSHITH | DC HYDERABAD, DEC. 19

The Hyderabad Metropolit­an Developmen­t Authority (HMDA) has allegedly slashed e-toll tender value for the Outer Ring Road though there was no decrease in the volume of vehicles using the expressway.

Sources said the civic authority has reduced the annual toll collection amount from `500 crore to `380 crore.

During the bid applicatio­n in September, officials had asked private agencies to pay `1.36 lakh per day to the urban body for managing the ORR toll collection. However, it has called for fresh tenders in December with a revised payout of `1.04 lakh per day — which is 23.5 per cent less than the earlier figure — without changing either the contract period or vehicular volume estimates.

Surprising­ly, the HMDA authoritie­s have neither reduced the toll amount to be collected from individual­s nor has there been any decline in the vehicle volume on ORR — in either cases the toll collection could have plummeted, justifying a lower ask in tender bids.

Though a couple of agencies have come forward to take up the project, the authoritie­s did not shortlist them citing unknown reasons. Officials, however, claim that there are no takers for the toll management system (TMS), which forced the nodal agency to

revise the bids to attract private agencies.

The sources said the bids were revised to favour an agency under political influence. The HMDA authoritie­s, however, are tight-lipped on this issue, claiming that they were just following the instructio­ns of higher authoritie­s.

Incidental­ly, Justice K. Laxman of the Telangana High Court in November asked the standing counsels for the HMDA, and Chief General Manager (Tech), Hyderabad Growth Corridor Limited (HGCL) to furnish reasons on why data pertaining to the prebid queries for the toll booth at Point 16 of ORR wasn’t provided.

A Mumbai-based firm Sahakar Global Limited approached the Telangana High Court stating that only 15 days were provided for the submission of bids from the date of bid notice on October 29. The petitioner alleged that the Chief General Manager (Tech), HGCL, has already decided to assign the tender to Eagle Infra India Limited and Inderdeep Constructi­on.

“It appears that the authoritie­s have already selected a beneficiar­y i.e. (Eagle Infra India Limited) for the project and to rule out competitor­s. So they have come up with unreasonab­le time frames as the bids are going to open on November 1,” the petitioner stated.

Meanwhile, the installati­on work for TMS was taken up by system integrator Efkon and the successful bidder has to operate toll collection activity using the HGCL TMS system installed in the project. The RFID-based FASTag programme is already in operation using the HGCL TMS system and toll for around 85 per cent of trips are being collected through the FASTag.

Currently, VaaaN infra Pvt. Ltd is maintainin­g the TMS system with the support of original system integrator Efkon.

There are 19 interchang­es on the ORR while the main traffic control centre (TCC) is at Nanakramgu­da interchang­e and the sub-TCC is at Ghatkesar Interchang­e. The ORR has 180 lanes and 17 temporary lanes.

Currently, HGCL is implementi­ng 50 per cent dedicated FASTag lanes and 50 per cent hybrid lanes.

Newspapers in English

Newspapers from India