Hindustan Times (Bathinda)

Apex court lifts stay on stalled projects under Char Dham all-weather road plan

The top court said the stay will however continue on those projects which are yet to begin under the plan until the environmen­t clearance is taken by the NGT authoritie­s

- Nihi Sharma nihis.sahani@htlive.com ■

DEHRADUN:THE Supreme Court on Friday lifted its stay on certain stalled projects under the central government’s ambitious Char Dham highway developmen­t plan, which aiming to provide allweather connectivi­ty to the circuit comprising four pilgrimage sites — Yamunotri, Gangotri, Kedarnath, and Badrinath — in Uttarakhan­d.

The SC said the stay will however continue on those projects which are yet to begin under the plan till the environmen­t clearance is taken by the authoritie­s.

The bench headed of Justice Rohinton Fali Nariman and Justice Vineet Saran also stayed a paragraph in the National Green Tribunal (NGT) order passed on September 26 last year which said that these projects did not require Environmen­tal Impact Assessment Approval/environmen­t Clearance in terms of the notificati­on of Ministry of Environmen­t & Forests.

On October 22 last year, the apex court had stayed the NGT order clearing the entire ambitious Chardham project in Uttarakhan­d. The court directed the Union ministry of road transport and highways to file its affidavit on a plea seeking a stay on the order the National Green Tribunal (NGT), which had cleared the projects and set up a committee to oversee it.

The court said the affidavit, to be filed within eight weeks, must indicate details of the ongoing projects specifying the stretch where hills have been cut and trees have been felled.

Dehradun-based NGO, Citizens for Green Doon (CGD) had challenged the NGT order dated September 26, 2018, which, in its Paragraph 46, had outlined that no environmen­t clearance (EC) was required. ““Accordingl­y, these projects did not require EIA Approval/environmen­t Clearance in terms of the Notificati­on of MOEF&CC dated September 14, 2006 and amended on August 22, 2013...” it had read.

At the outset, Additional Solicitor General Pinky Anand appearing for the Centre along with advocate Balendu Shekhar, said that the NGT has cleared the project and all due procedure were followed.

Advocate Sanjay Parikh, appearing for the NGO petitioner, said 900km of the road widening highway project was illegally divided into segments in order to avoid prior environmen­tal clearance. This clearance is mandatory for national highway covering 100km or above. He had added that mountains in Uttarakhan­d were very fragile and if environmen­t concerns were not taken care of, a tragedy like the Kedarnath flash flood of 2013 can happen again.

The NGO had stated that the project has been “mischievou­sly divided” into segments to avoid taking green clearance under the environmen­t impact assessment (EIA) notificati­on, 2006. Over 26,000 trees have been felled, claims the NGO.

“The Supreme Court has banned any new constructi­on activity until EC is obtained. The ongoing works could continue. The MORTH has been asked to file affidavit on the works done so far,” Himanshu Arora, secretary of the NGO said.

Parikh said that if the project was allowed to go on, an irreversib­le damage would be done to the ecology which would be equal to damage done by 10 hydro power projects.

He said that NGT order giving clearance to the project should be stayed as there were gross violation of environmen­tal norms.

The court agreed that prior environmen­tal clearance for the project is needed and therefore, stayed the judgement of NGT that says ‘no environmen­tal clearance’ is required.

The bench, however, said that it will not stay the NGT order in entirety. The bench made it clear that the project could proceed only if the environmen­tal clearance is obtained.

The apex court said that mountain cutting and tree feeling had been done for ongoing projects and therefore they shall continue to avoid further damage to the sensitive route. It also hoped that government and related agencies ‘will not commence any new tree felling activity or cutting mountains involving slope destructio­n and muck dumping’ which would be considered violation of the order.

The NGO also claims that massive damage has been posed due to the project which has led to human mortalitie­s during the rainy season. They reported that seven labourers were killed in the landslide on the yatra route. The ministry of road transport had earlier submitted before NGT that the along 16 stretches the physical progress of widening work if between 0%-25%.

The top court had on November 26 sought the Centre’s response on why it should not stay the NGT order clearing the project. On September 26, the NGT had constitute­d a committee to monitor the road project while giving its nod with some safeguards in view of public interest and the country’s security.

The committee headed by former Uttarakhan­d HC judge Justice UC Dhyani was set up to overseeing the implementa­tion of the Environmen­t Management Plan (EMP) of the project.

The NGO had said that the environmen­t clearance was must for the project and the ongoing work was “blatantly illegal”.

 ?? HT PHOTO ?? The SC has also asked the ministry of road transport to submit an affidavit within eight weeks on a plea seeking a stay on an NGT order which had cleared the projects.
HT PHOTO The SC has also asked the ministry of road transport to submit an affidavit within eight weeks on a plea seeking a stay on an NGT order which had cleared the projects.

Newspapers in English

Newspapers from India