Hindustan Times (Delhi)

RIL’s KG exploratio­n without green approval

-

CONTINUED FROM P17

“It had come to the notice of the ministry that RIL has started drilling operations without prior environmen­t clearances,” the letter says.

The letter further states, “The ministry of petroleum vide their letter dated Sept 12, 2002 informed the environmen­t ministry that RIL vide its letter dated August 2002 has indicated to director general of hydrocarbo­ns (DGH) that two wells have been drilled and a third well is under drilling in KG-DWN-98/3 (KG-D6).”

RIL sought clearance in December 2001, but began work without getting the certificat­e and had even completed drilling in two wells by August 2002. Its clearance, however, came only in October 2002.

Former secretary and planning commission advisor, EAS Sarma told Hindustan Times, “From the correspond­ence between the above ministries, it is clear that RIL started drilling three wells even before obtaining the mandatory clearances. The company made it a fait accompli by resorting to this. The fact that the ministries concerned acquiesced in this shows that they were under pressure”

One year after it got post facto clearance in October 2002, RIL changed the number of wells to be drilled in each of the five blocks in KG basin. In October 2002, RIL had taken clearance for eight wells for KGD6 block, which it changed to 18 in September 2003. Similarly, for KG20, the proposed wells changed from six wells earlier to two wells in September 2003. The basin is divided into geographic­al areas and is termed as blocks.

MoEF accepted this and in letter to the then RIL group vice-president AN Sethuraman on November 6, 2003, PL Ahujaral, additional director, said, “…ministry coveys its permission for drilling of 28 wells as per the revised numbers of each of the block within the same block….”

Environmen­talists object to the change in number of wells. “Every block has different dynamics and should have been reassessed. A fresh proposal should have been given and based on that, fresh environmen­t clearances should have been given,” said Chandra Bhushan, deputy director general, Centre for Science and Environmen­t.

According to the environmen­t clearance issued in October 2002, “...In case of deviations or alteration­s in the project proposal from those submitted to this ministry for clearance, a fresh reference should be made to the ministry to assess the adequacy of conditions imposed and to add additional environmen­tal protection measures required, if any.” The ministry did not respond to whether any fresh assessment was made, based on the changes proposed by RIL.

 ??  ??
 ??  ??

Newspapers in English

Newspapers from India