Polluting Badarpur power station to restart operations

- Sweta Goswami sweta.goswami@hidnustant­imes.com

THERMAL PLANT The coalfired power plant was shut down in November after air pollution touched unpreceden­ted levels

New Delhi: After remaining shut for the past three months,the Badarpur Thermal Power Station (BTPS) will begin operations on Thursday.

The Supreme Court-appointed Environmen­t Pollution Prevention and Control Authority (EPCA) had ordered the coalfired plant to shut down in November last year because of alarming pollution levels.

It was set to be open to open on Wednesday but the National Thermal Power Corporatio­n (NTPC) Limited said they are yet to receive an order from the Delhi Pollution Control Committee (DPCC) for re-opening the plant. DPCC said the order would be issued on Wednesday and NTPC could start operation on Thursday.

“We are preparing the notificati­on right now and it will be issued only on March 15(Wednesday). Once they receive the letter, NTPC will be allowed to start BTPS on any day, starting March 16. The plant will be run until further directions are issued,” a DPCC official said.

EPCA has proposed shutting the polluting station as a thermal power plant by July 2018. The Delhi power department, which has been asked to submit the closure plan, has maintained that the 705MW coal-fired plant needs to operate, at least during the summer months, till the Tughlaqaba­d sub-station is commission­ed to meet the power demand of south Delhi.

“The thermal power plant has to function to meet the peak demand during summers, which may touch 6,600MW this year,” a power department official said.

Till the Tughlaqaba­d sub-station is commission­ed, DPCC has been directed to appoint NEERI (National Environmen­tal Engineerin­g Research Institute) to monitor the fly ash pit and the air quality in and around the station. As per the Graded Response Action Plan, the plant will func- tion till October 15, EPCA member Sunita Narain said.

However, the NTPC-run power plant will be allowed to function subject to a set of conditions, including the emptying of its fly ash pit within a time frame and timely commission­ing of the 400-KV Tughlaqaba­d sub-station by June 2018.

 ?? HT PHOTO ?? Badarpur Thermal Power Station is located near Faridabad. The power plant is run by NTPC
HT PHOTO Badarpur Thermal Power Station is located near Faridabad. The power plant is run by NTPC