Improper planning hiked flyover cost by ₹546cr: Report

- Vibha Sharma vibha.sharma@htlive.com

NEW DELHI: The North Delhi Municipal Corporatio­n’s preliminar­y audit report on Rani Jhansi flyover stated that the project has an additional 18 years to be completed owing to improper planning and inadequate monitoring. This also resulted in the cost being escalated by a whopping ₹546.5 crore, the report said.

The report compiled by the office of the municipal chief auditor of north corporatio­n, on the directions of the standing committee, pointed out that the project, which could have been completed in five years, took an additional 18 years ( 23 in total) and resulted in a 300% escalation in project cost. The original estimate was ₹177.7 crore but the final cost was ₹724.2 crore.

The planning for the 1.6km flyover, which starts near St Stephen’s hospital and extends till Filmistan Cinema, and was meant to which is meant to decongest areas in central Delhi, started in 1998. However, constructi­on started only in 2008 . It was inaugurate­d in October. The report also mentioned that the work on the project picked up pace only after the interventi­on of the Lieutenant-governor and the Delhi high court. “Between 2008 and 2013, no significan­t efforts were made at any level to expedite the constructi­on work, early acquisitio­n of land needed as well as the shifting of utilities,” the report said.

“This being one of the high value projects executed by the MCD, it required high-level monitoring and utmost attention but as per records, there was no review of progress or coordinati­on with outside agencies between 2008-2013,” it said.

Veena Virmani, North corporatio­n standing committee chairperso­n, said the report will need a final approval from the commission­er. “It needs to come as preamble from the commission­er and only then can we take further action. Also, we will give an opportunit­y to the department concerned to reply.”

The report also mentions various expenditur­e that could have been avoided had there been proper planning and coordinati­on. “There were so many avoidable expenditur­e such as an amount of ₹8 crore spent on land acquisitio­n, and ₹6 crore incurred due to a delay in providing land for shifting utilities. There was a wasteful expenditur­e of ₹6.73 lakh on consultanc­y,” the report said.

Meanwhile, commuters continue to complain about congestion on the road beneath flyover, especially near Azad Market Traffic Signal,filmistan and Baraf Khana. To resolve the problem, the North corporatio­n had a meeting with agencies concerned, including traffic police, last week. “We had also written to the PWD to construct a central verge near Baraf Khana, Tis Hazari and Filmistan to regulate traffic movement,” Virmani said.

 ?? HT ARCHIVES ?? The report said the work on the project picked up pace only after the interventi­on of the L-G and the high court.
HT ARCHIVES The report said the work on the project picked up pace only after the interventi­on of the L-G and the high court.