Hindustan Times (East UP)

Centre allows transmissi­on lines in flamingo sanctuary

- Prayag Arora-Desai prayag.desai@htlive.com FILE

MUMBAI: The Union environmen­t ministry’s expert appraisal committee (EAC) for coastal regulatory zone (CRZ) clearances has given a go ahead for setting up 47 transmissi­on towers in Mumbai, a portion of which will pass through the Thane Creek Flamingo Sanctuary for less than half a kilometre.

The project, which will help to meet growing power demand for power in suburban Mumbai, will also result in the clearing of over 1,800 mangrove trees along 14.5 km across 71 hectares of forest. Mangroves and saltpans in Airoli, Mulund, Bhandup, Kanjurmarg, Nahur and Vikhroli will be impacted by this project, as per informatio­n submitted to the forest department by the project proponent.

According to a letter of interest issued to a private power company Adani Transmissi­on in 2019, the project is set for completion by March 2022. However, before proceeding with physical works, Kharghar-Vikhroli Transmissi­on Pvt Ltd’s special purpose vehicle will also have to obtain permission from the forest department and National Board of Wildlife, which is currently under process. The Bombay high court in February this year had already granted permission for cutting mangroves.

The environmen­t ministry cleared the project in its 270th meeting related to CRZ projects on August 11, after the Maharashtr­a State Coastal Zone Management Authority (MCZMA) recommende­d the project for clearance in June this year. At the time, it was noted by the committee that around 6,000 mangrove trees will be affected by the project, over and above those which are slated to be felled.

Of the 47 towers proposed to be installed to facilitate supply of power from Airoli in Thane to Vikhroli in Mumbai, 44 will be installed in protected CRZ area, of which 34 will be installed in CRZ-IA areas.

The Union ministry has upheld all recommenda­tions of the state authority while sanctionin­g the project. “Bird diverters should be installed in transmissi­on line so as to avoid accidental collision of birds ie flamingos etc, with support of reputed institutio­ns,” the EAC noted.

The forest department will also have to carry out compensato­ry plantation­s of mangroves as well as afforestat­ion of degraded forest land twice the area being diverted for the project. The net present value of the forest area has been calculated at around ₹9 lakh per hectare.

According to a presentati­on made to the Union environmen­t ministry by the project proponent earlier on August 11, “The proposed transmissi­on lines project would enable additional power supply of 1,000 MW to be brought into Mumbai and suburbs, thereby helping to meet the ever increasing energy demands of the city.

The execution of such a public utility project will help the city of Mumbai in getting economic power from other sources, thus benefittin­g the consumers of Mumbai, in terms of assuring 24X7 supply at competitiv­e rates.”

 ??  ?? The transmissi­on lines project is set for completion by March 2022.
The transmissi­on lines project is set for completion by March 2022.
 ??  ??

Newspapers in English

Newspapers from India