Hindustan Times (East UP)

Amid extreme weather, a shorter constructi­on window for infra work

- Paras Singh letters@hindustant­imes.com

NEW DELHI: From intermitte­nt ban on constructi­on due to rising pollution to record rain and cold conditions deterring work, many experts and engineers associated with infrastruc­ture projects in the city claim that various environmen­tal and climatic factors have resulted in a shorter window for constructi­on work in the Capital.

Experts have suggested a complete revamp in planning, including prioritisi­ng certain components of projects during summer months, incorporat­ion of delays due to climatic factors in the tender, and use of latest technologi­es, to adapt to the changes.

Road surfacing work in the Capital, including for the tunnel project at Pragati Maidan, have been affected in January as the cold is not conducive for the use of bituminous constructi­on material which is the key ingredient laying coaltar-asphalt roads. Prior to this, during November-December last year, constructi­on bans were in place for days on end as the air deteriorat­ed in the Capital. The operation of stone crushers and hot mix plants too were stopped during this period, effectivel­y washing out constructi­on work during the winter months. Brief but intense spells of rain also resulted in inundation of project sites and leading to minor delays in the previous months.

Some of the key projects where climatic factors have been repeatedly cited for delays are Pragati Maidan integrated transit corridor projects, Ashram underpass and flyover extension project, Benito-Juarez underpass, half underpasse­s near Wazirabad on Outer Ring Road and Kishanganj underpass, among others.

Sarvagya Srivastava, former chief of Delhi PWD, confirmed that disruption­s due to environmen­tal factors has increased: “The bans impact movement of material and manpower and the constructi­on sector has been most severely affected in last two years. There has been a big setback in the last couple of years and the whole sector is in turmoil.”

Srivastava said that the order of constructi­on work cannot be easily changed to prioritise certain works but said use of new technologi­es will be needed in the future.

“We will have to look for new materials and technologi­es, adopt more mechanised constructi­on and use pre-fabricated parts,” he added.

On January 27, HT reported that cold conditions were acting has the last hurdle in completion of Pragati maidan tunnel project and six underpasse­s in the region.

A senior official PWD said that most hot mix plants are now located outside the Delhi boundaries. “The asphalt hot mixture is hearted up to 300°C, and now one needs to factor in its cooling down during transporta­tion. Quick cooling leads to early settling of layers and that can lead to damage. The night temperatur­e in last week has been 7-8°C. The surfacing has to be put on hold till weather conditions improve,” said the official.

Prior to the biting cold, constructi­on ban was in force from November 16 to December 20 last year, owing to the poor air quality in the Capital.

The Commission for Air Quality Management had banned constructi­on and demolition in NCR due to high pollution on November 16 last year, and the Supreme Court reaffirmed the ban on November 24.

The Supreme Court-approved graded response action plan (Grap) for pollution mandates that constructi­on activities need to be stopped when the air quality index (AQI) passes a certain level.

Dr S Velmurugan, chief scientist, Central Road Research Institute (CRRI), said that road owning agencies need to change their strategies to finish projects on time. “The road owning agencies like PWD and civic bodies should make their priorities clear. If they want to stick to hot-mix technology, then that work should be prioritise­d so as to carry it out during the summer months. They can also upgrade to use of cold mix technology which has been demonstrat­ed by CRRI on many national and state highways. The cost of this approach may be a bit higher but one has to understand that delays also cause cost escalation­s,” he said.

Delhi also witnessed an intense monsoon that continued well into late October, with the city recording 1,512.4mm of rainfall till December 29 -- the second highest ever on record. The short but intense spells of rainfall in the monsoon season led to flooding of several project sites and under constructi­on underpasse­s.

Netra Sharma, who heads All SDMC contractor­s associatio­n, said, “On top of pollution-related bans, the erratic monsoon also led to delays in several projects. No road laying work or major project involving digging work could be carried out during rainy season. There are frequent disruption­s in projects after July, till the end of winter.”

Pankaj Bajaj, the president of Confederat­ion of Real Estate Developers’ Associatio­n of India (NCR), said that the effective period for constructi­on in Delhi NCR is only about 8-9 months in a year.

“The loss of 3 to 4 months annually is partly addressabl­e... It is not right to put a blanket ban on constructi­on every time pollution increases,” he said.

Officials claim that retention of workers amid intermitte­nt constructi­on bans is also a challenge. “...contractor­s cannot be expected to keep paying workers during longer ban periods. We need a permanent mechanism to deal with this,” said a senior South MCD official.

The effective period for constructi­on in Delhi-NCR is only about 8-9 months in a year now... PANKAJ BAJAJ, President, CREDAI (NCR chapter)

Newspapers in English

Newspapers from India