Labour shortage hits Kharar flyover work, but admn hopeful of meeting Sept deadline

- Shailee Dogra shailee.dogra@hindustant­imes.com

MOHALI: As a result of mass migration of labourers to their native states in wake of the Covid-19 outbreak, work on the Kharar flyover has taken a hit.

The shifting of the overhead high-tension power cables to be undertaken by the Punjab State Transmissi­on Corporatio­n Limited (PSTCL) is yet to be completed and is holding up the constructi­on work.

“We are planning to open the flyover’s Khanpur to Desumajra stretch for public by July end,” said Himanshu Jain, Kharar sub-divisional magistrate (SDM).There were three poles to be shifted. Out of which two have been shifted, while the one at Khanpur is yet to be shifted to allow elevation. Jain said, “PSTCL was facing labour issues, but we have directed them to complete the shifting of high-tension wires by June 20.”

Earlier, in February, Punjab public works minister Vijay Inder Singla, in reply to question by Kharar MLA Kanwar Sandhu, said the new deadline for the Balongi-Khanpur flyover project was September 2020.

After reviewing the progress of the work, Jain said, “I was assured in the meet that service lanes will be completed by the first week of June. When the new Khanpur bridge to comes up by July end, the old one would be demolished and the entry and exit points of the flyover would be constructe­d.”

EFFORTS ON TO BRING BACK SKILLED LABOUR

“Skilled labourers deployed by L&T are stuck in Uttar Pradesh. We are tying-up with authoritie­s in Uttar Pradesh to get them back and add pace to work,” added Jain, who is overseeing the progress of the flyover.

However, the work of making service lanes and constructi­on of the Kharar flyover has picked pace. About 375 local labourers have been deployed at the site to complete the work. Traffic has been diverted to one side of the flyover which is leading to bottleneck­s. The 10-km KhararChan­digarh road expansion project that entails constructi­on of two flyovers and three bridges and the authoritie­s is struggling to meet the deadlines. In the past four years, only 68% work has been completed.

 ??  ??