Hindustan Times (Jalandhar)

Kharar flyover delayed again, deadline pushed to November

Migration of labourers, shifting of overhead power cables latest roadblocks

- Hillary Victor hillary.victor@htlive.com

MOHALI:Expected to be completed by September after missing multiple deadlines, the Chandigarh­Kharar flyover has been delayed again — this time by two more months, now getting the seventh deadline as November 2020.

The National Highways Authority of India (NHAI) had handed over the ₹368-crore project to Larsen & Toubro, that began constructi­on in November 2015. It was to be completed in three years by December 2018.

But over four years later, only 70% work has been completed, with the project being pushed six times to January 2020, March, June, July, September and now to November.

After multiple roadblocks impeding the project’s progress, authoritie­s have now cited labour shortage and shifting of the overhead high-tension power cables as reasons for further delay.

Work on the flyover was suspended on March 22 after the nationwide lockdown to prevent the spread of Covid-19, but was resumed from April 20, with authoritie­s hoping it will finish by September amid restrictio­ns on movement of traffic.

Kharar sub-divisional magistrate (SDM) Himanshu Jain, who is supervisin­g the project, said the executing agency was facing labour shortage and was waiting for shifting of high-tension power cables. “To shift the cables, we need to shut down the power supply, but that will cause inconvenie­nce to residents. We are working on finding a way, and will accomplish the task by June 10,” he said.

NHAI project director Krishnan Sachdeva said they were doing their best to complete the project by November end. “Due to Covid-19 lockdown, we are working with only 50% manpower, as the remaining workers have returned to their native states,” he said.

The national highway where the flyover is coming up connects Chandigarh to parts of Punjab, besides Jammu and Kashmir and

Himachal Pradesh.

This leaves Kharar as a major bottleneck, with around 50,000 vehicles crossing the stretch daily.

“The authoritie­s concerned are not bothered about the inconvenie­nce to commuters and keep indulging in blame game. It is a challenge to cross the stretch, which often even delays ambulances,” said Kamaldeep Singh Tiwana, a resident of Kharar.

WORK WAS SUSPENDED ON MARCH 22 AFTER THE NATIONWIDE LOCKDOWN BUT WAS RESUMED FROM APRIL 20

 ??  ??
 ?? GURMINDER SINGH/HT ?? The flyover’s constructi­on began on the Chandigarh-Kharar road in November 2015.
GURMINDER SINGH/HT The flyover’s constructi­on began on the Chandigarh-Kharar road in November 2015.

Newspapers in English

Newspapers from India