THE PROJECT TIMELINES SET BY THE CM
Construction of the main gate of the historical Sheesh Mahal, Satkhanda Park, Ghantaghar and beautification of the Picture Gallery Park to be completed by December 31, 2014. Beautification of the Sheesh Mahal pond situated on the Durga Devi temple road in Husainabad ward by December 31, 2014. Undergrounding of the power systems from Teele Waali mosque in Hussainabad to Jama Masjid turn by December 15, 2014. Widening and beautification of the road from Hussainabad Teele Waali Maszid to Jama Masjid turn by March 31, 2015. Construction of community centre in Picture Gallery complex and beautification of the Raees Manzil Park by January 2015. Construction of Mehndi Ghat project on the kilometer 1.870 of the right hand embankment upstream of Gomti river from the Harding Bridge by January 2015. Beautification of the Clock Tower, Ghantaghar Pond and Picture gallery complex by December 31, 2014.