Plan cultural calendar, events along Gomti: CS

- HT Correspond­ent

The city’s lifeline – Gomti River undergoing a multi-crore makeover – would soon have a cultural calendar of its own to attract domestic and foreign tourists. Authoritie­s involved in the riverfront developmen­t programme have been asked to plan sports activities, leisure, cultural and entertainm­ent events along the banks of the river that runs through the city.

The first such big event has been planned in the form of a cricket match in the newly built cricket stadium cum sports complex near Shaheed Path in Gomti Nagar Extension on October 2. But while the city would have to wait to witness a clash of internatio­nal level, the October cricketing event would see cricket teams from rural areas contesting for the winner’s cup.

Water sports would be another attraction to watch out for. Chief secretary Deepak Singhal, who reviewed the progress of ongoing beautifica­tion and developmen­t work on Gomti River on Wednesday, has asked the officials to come up with an events’ calendar within 15 days. Apart from entertainm­ent and cultural events, the plan would also include holding exhibition­s to showcase local talent in embroidery and crafts, specially chikan and zardozi.

The CS also asked the authoritie­s to launch a publicity campaign through print, electronic media and social platforms and inform the people about the work being done on the riverfront.

“We should hold events every month to attract tourists and make the river a hub of cultural programmes and entertainm­ent activities,” Singhal said adding that artisans of famous Lakhnawi Chikankaar­i and other handicraft­s should be contacted for this purpose.

The CS directed principal secretary and head of department of Irrigation to take appropriat­e steps for installati­on of a worldclass fountain at Gomti riverfront

We should hold events every month to attract tourists and make the river a hub of cultural programmes and entertainm­ent activities. DEEPAK SINGHAL, Chief secretary

within the cost approved by the Expenditur­e Finance Committee.

He said that constructi­on of cycle track along with other developmen­t works should be carried out along the banks of Gomti River on priority.

The irrigation department officials were told to expedite plantation and greenery work along the banks and finish it by August 15.

They were asked to nominate a department­al nodal officer along with sector-wise deployment of one assistant engineer and a junior engineer.

District magistrate, Lucknow was made the nodal officer for tree-plantation and asked to coordinate with executing agency and officials of forest and irrigation department­s for smooth execution of the work. September 15 was set as the deadline for completing work on the proposed rubber dam plant.

The officials were told to keep 15-20 boats ready to remove Jalkumbhi (weeds) from the river and take steps to ensure that untreated sewer water did not flow into the river.