Hindustan Times (Patiala)

Delayed loop mired in legal, financial tangles

- hrao@hindustant­imes.com Hitender Rao

CHANDIGARH: The 136-km Kundli-Manesar-Palwal (KMP) Expressway, thrown open to the public by Prime Minister Narendra Modi on Monday, is a project behind schedule by over nine years having remained mired in and legal and financial complicati­ons.

The Haryana State Industrial and Infrastruc­ture Developmen­t Corporatio­n (HSIIDC) was appointed as the executing agency by the state government for the developmen­t of the expressway project on built-operate-transfer (BOT) basis. The estimated cost of the project was about ₹1,200 crore and that of land and allied expenses was Rs 1,110 crore.

THE FIRST CONTRACTOR

The previous Congress government had allotted the work for developmen­t of expressway to M/s KMP Expressway­s Ltd, a special purpose vehicle (SPV) formed for the purpose. The concession agreement was executed by the HSIIDC with the concession­aire on January 31, 2006. The constructi­on period was three years with commercial operation date (COD) as July 29, 2009.

Since the concession­aire M/s KMP Expressway­s Ltd could not complete the project, the BJP government in the state terminated the contract in March, 2015. The project faced a number of hindrances. There were land acquisitio­n issues of interchang­es and ramp plazas because of litigation­s by landowners, operative stay granted by the courts, permission from the Railways for rail over bridges, shifting of electricit­y lines, demands by local residents for modificati­on in the crossings and structures.

To add to the delay, M/s KMP Expressway Ltd, initiated arbitratio­n proceeding­s in October 2013 raising disputes over change of scope issues, alleged delay in conveying decision on use of fly ash and thereby claiming damages of Rs 13,920 crore.

The HSIIDC on the other had filed counter-claims of ₹17,973 crore as on February 2017. The money lenders of the previous concession­aire also filed damages of HSIIDC Rs 1,737 crore against HSIIDC.

The Corporatio­n also filed counter claims amounting to Rs 8,518 crore. The disputes are being heard by arbitrator­s and carry possible financial implicatio­ns for the government. The concession­aire had defaulted of its various obligation­s since the start of the project and there were also disputes between the members of the special purpose vehicle which caused delay of over five months in achievemen­t of financial closure.

BAILOUT PACKAGE

Despite repeated completion deadlines, the concession­aire continued missing them, giving one justificat­ion or the other. The delay was also not firmly tackled by the previous Congress government, which decided to go beyond the provisions of the concession agreement, thereby terminatin­g the concession agreement with mutual consent and giving the project to a new company.

As part of the “bailout” plan, the Congress government

decided the terminatio­n payment of about Rs 1,300 crore to be paid to the concession­aire and the project lenders by the new company.

The ₹,300 crore fixed as terminatio­n payment was on account of the work done on the delayed project by the then contractor. However, this was rejected by the BJP government, which came to power in 2015.

SECOND CONTRACTOR

The present government terminated the contract on in 2015 and decided to get this project completed by dividing into two sections — Kundli-Manesar section and Manesar-Palwal section.

For the 52 km Manesar-Palwal section, work was allotted in March 2015 to a joint venture of M/s KCC Buildcon Pvt. Ltd. – Dilip Buildcon Pvt Ltd. with contract value of Rs 483 crore. The work in this section completed on March 31, 2016. Work of developmen­t of 84 kilometre Kundli-Manesar stretch was allotted to M/s Essel Infraproje­cts Limited in July, 2015 with the project cost of Rs 1,863 crore. This stretch was thrown open to public on Monday.

 ?? HT PHOTO ?? The KundliMane­sarPalwal Expressway in Gurugram.
HT PHOTO The KundliMane­sarPalwal Expressway in Gurugram.

Newspapers in English

Newspapers from India