Hindustan Times (Ranchi)

CAG points to financial lapses in flyovers’ constructi­on in Patna

- Arun Kumar arunkr@hindustant­imes.com

PATNA: Bihar’s capital Patna has seen a chain of flyovers over the last one decade, but the recent report of the Comptrolle­r and Auditor General (CAG) of India for the year ending March 31, 2019 has underlined that “flyovers were being constructe­d without ensuring the availabili­ty of drawing and design, tenders were invited before obtaining administra­tive approval and payments were made prior to technical sanction”.

“Such practices were also reported to the government by the CAG for the year ending March 31, 2010, and audit report (PSUs) for the year ending March 31, 2015. However, the Bihar government is yet to address these significan­t issues which go against the financial propriety and prudence,” says the report, tabled in the Bihar Legislativ­e Assembly last week.

“There is neither transparen­cy in the selection of consultant­s nor was payment linked to deliverabl­es/progress of work,” the report says, adding that it resulted in time overrun and undue benefits to consultant­s in violation of Bihar Finance Rules.

The audit was carried out for three flyovers in Patna — multijunct­ion interchang­e at Bailey Road (Lohia Path Chakra), R-Block flyover and Karbigahiy­a flyover connecting to Chiraiyata­nd flyover — entailing a total cost of Rs 588 crore. All three suffered from time overrun of 19-30 months.

“Scrutiny of records in June 2019 revealed that while planning two projects (Karbigahiy­a and R-Block flyovers), no traffic survey was conducted to assess the requiremen­t of flyovers. In

Such practices were also reported to the govtt by the CAG for the year ending March 31, 2010, and audit report (PSUs) for the year ending March 31, 2015. However, the govt is yet to address these significan­t issues.

AUDIT REPORT

the absence of any traffic census/data, it could not be verified whether these flyovers were properly designed and whether the number and width of traffic lanes provided in flyovers were sufficient to cater to requiremen­t. It was noticed that the technical sanctions of the projects were accorded on a piecemeal basis as stage wise technical sanction was given. Even after four years of commenceme­nt of work, technicall­y sanctioned drawing and design for the entire length was not finalised till December 2019, though agreements were entered into and payments made to contractor­s,” says the report, rejecting the argument of the Bihar Rajya Pul Nirman Nigam in June 2020 that tenders were invited prior to administra­tive approval in the interest of work and to minimise time span.

In case of Lohia Path Chakra, the audit objected to excess payment of Rs 7.44 crore to a consultant appointed on nomination basis without any justificat­ion for single-source selection in violation of Bihar Finance Rules, to which the management of the Nigam did not offer any comment.

 ?? HT FILE ?? CM Nitish Kumar inspected under-constructi­on Lohia Path Chakra in Patna last year.
HT FILE CM Nitish Kumar inspected under-constructi­on Lohia Path Chakra in Patna last year.

Newspapers in English

Newspapers from India