Transmissi­on firms eye ₹20K-cr gain from solar boost

- Gireesh Chandra Prasad gireesh.p@livemint.com

The government’s decision last month to double solar park capacity to 40,000 mega watt (MW) in three years has opened up a new business opportunit­y worth up to ₹20,000 crore for transmissi­on firms.

Adding new 50 ultra-mega solar parks to the 34 under constructi­on in 21 states, as decided by the Cabinet on February 22, will need to significan­tly widen the green energy corridor — the transmissi­on network for the solar parks — an official at Solar Energy Corp. of India, a stateowned company in charge of implementi­ng various solar power projects, said.

The ongoing ₹13,000-crore green energy corridor-II project connecting the 34 parks under constructi­on and new transmissi­on projects will be identified keeping in mind the location of the new parks, said the official, requesting anonymity.

Transmissi­on networks within the state where projects come up will be assigned to transmissi­on utilities by the states, while inter-state projects will be assigned by the central government. Since constructi­on of solar parks takes way less time than setting up a transmissi­on corridor, transmissi­on projects that need quick execution will be assigned to central or state transmissi­on firms, while those for power plants that will come up at a later stage are likely to be auctioned as it affords sufficient time for a tariff-based bidding, an official in the power ministry said requesting anonymity.

According to I.S. Jha, chairman and managing director of Power Grid Corp., which prepared the roadmap for the green energy corridor-II, not all the proposed new solar parks may come up at new locations and many could be in the solar and land resource rich states such as Madhya Pradesh, Rajasthan, Tamil Nadu and Gujarat where such parks are already underway.

“The required additional transmissi­on capacity may be a mix of inter-state and intra-state. In the case of a new solar park, generally, the cost of transmissi­on comes to ₹50 lakh to ₹1 crore per mega watt depending on the location,” said Jha.

Under the green energy corridor project - II, 32 transmissi­on projects-- ₹8,041 crore of interstate networks and ₹4,745 crore of intra-state network-- are being constructe­d.

Under the original 100 gigawatt (GW) solar capacity addition plan, 20 GW was to come from solar parks which needed high-end transmissi­on network and 40GW each from roof top projects and distribute­d power projects, both of which require very limited transmissi­on network. This has now been recalibrat­ed to provide for 40 GW of solar park capacity, merging with it a part of the planned distribute­d solar capacity.