Paint job, not repair work, awaited the bridge that fell

- Tanmay Chatterjee and Avijit Ghosal letters@hindustant­imes.com

KOLKATA: THE GOVT HAS ALSO DRAWN UP ELABORATE PLAN TO MARK ONE MONTH OF THE DEATH OF FORMER PM ATAL BIHARI VAJPAYEE AS ‘KAVYANJALI DIWAS’

The West Bengal’s Public Works Department (PWD) issued tenders for Majerhat Bridge’s painting and surface repair even as its condition was deteriorat­ing on account of what experts now say were structural problems. A part of the 50-yearold bridge’s central section caved in on Tuesday, killing three persons and injuring 19.

Hindustan Times has reviewed 106 tenders the PWD’s Alipore Division, under whose jurisdicti­on the bridge comes, floated between June 6, 2014 and August 31, 2018. Only eight of them were floated for the two flyovers in the division’s jurisdicti­on. Three tenders were issued for painting and surface repair of Majerhat Bridge. Five were floated for Taratala flyover, less than 100 metres away.

The last tender for “surface repairing of a service road” of the Majerhat Bridge was floated on July 27. The project did not take off. The PWD , on August 10 issued a general memorandum saying the appearance of bridges and culverts were not up to the mark. “Therefore, it is decided that all bridges and culverts are to be painted after cleaning the same and repairing it, if necessary.” PWD minister Arup Biswas and principal secretary Arnab Roy could not be reached despite repeated attempts seeking comment.

Although PWD floated all the tenders, urban developmen­t minister Firhad Hakim did not specify which department was in charge of the Majerhat Bridge.

“The PWD maintains both flanks of the bridge and the road above. Only the portion that runs above the railway tracks is repaired by Eastern Railway. The Trinamool government cannot disown responsibi­lity,” said former PWD minister and Revolution­ary Socialist Party leader Kshiti Goswami.

“I cannot remember the year right now but our (the previous Left Front) government repaired portions of the bridge.”

Civil engineers pointed at two specific problem areas though they were not in a position to say to what extent these factors contribute­d to the disaster. “It is a monumental maintenanc­e failure. One, down the years, as the road on the bridge was repaired, the workers piled asphalt layer on layer, thereby increasing the dead load enormously,” said Kamal Saha, a civil engineer.

“Also think of the heavy vehicles that used to ply over the structure. There were no structural reinforcem­ents. Only some cosmetic work such as painting was done.”

Another engineer, who did not want to be named, said “engineerin­g maintenanc­e” was essential, not cosmetic dressing. “Steel beams exposed after the disaster show that water kept seeping through concrete and weakened the structure.”

Chief Minister Mamata Banerjee on Wednesday echoed Hakim’s Tuesday statement saying vibrations caused at the adjacent Metro Railway constructi­on site might have contribute­d to the disaster. Experts did not agree. “Had vibration caused by digging been powerful enough to crack portions of the bridge, then it would have affected the railways’ tracks long ago,” said an engineer on condition of anonymity.

 ?? PTI ?? Personnel of West Bengal Disaster Management Department carry out rescue and relief works at the site of Majerhat bridge collapse, in Kolkata late on Wednesday.