Hindustan Times ST (Jaipur)

Bullet train

-

“After finalizing the alignment in October 2017, we appointed consultant to decide the power requiremen­t for the project. After a detailed study, we have finalized the locations of substation­s and how much power will be required at how many locations. We have also tied up with power distributi­on companies so that they can start work on the transmissi­on lines,” NHSRCL manag- ing director Achal Khare said in an interview in November.

The official added that the consumptio­n estimates are in line with what similar networks elsewhere consume.

According to NHSRCL, traction power requiremen­ts are assessed by electrical works contractor­s that carry out power system simulation studies. The maximum projected train traffic and time table is simulated using software and the electric power requiremen­t at each power substation, location and spacing of substation­s is assessed. “The power requiremen­ts of all the 29 substation­s and locations were finalised by January 2018 and the power utility companies in Gujarat and Maharashtr­a were approached. The joint surveys with power utility companies were completed by April 2018. The utility companies are now going ahead with related works,” said a spokespers­on for NHSRCL.

As part of a green energy initiative, the Mumbai–ahmedabad bullet train corridor will tap solar energy at the rolling stock depots in Sabarmati and Thane, the High-speed Rail Training Institute in Vadodara, and Sabarmati HSR Complex.

Of the 508.17-km-long bullet train corridor, 155.76 km will be in Maharashtr­a, 348.04 km in Gujarat and 4.3 km in Dadra and Nagar Haveli. The Narendra Modi government has set the ambitious deadline of completing the project by August 15, 2022

Newspapers in English

Newspapers from India