Plan must pass the test of implementa­tion: Experts

- Risha Chitlangia

Monitoring and ensuring implementa­tion of the Delhi master plan provisions will be a big challenge, urban planners and experts said on Thursday -- a day after the Delhi Developmen­t Authority uploaded the draft of the MPD-2041 online seeking feedback from the citizens -- while pointing out that several provisions of the MPD2021, which is currently in effect, have not been implemente­d or are still in progress.

Regularisa­tion of unauthoris­ed colonies, preparatio­n of wardlevel local area plans, a redevelopm­ent plan for special areas, developmen­t of integrated freight complexes (IFCS), and shifting of wholesale markets from the city’s centre to these IFCS, and redevelopm­ent of old planned areas are some of the ambitious provisions in MPD-2021 that never saw the light of the day.

Experts say that several plans stayed on paper because of lack of stringent monitoring, complexiti­es in policy provisions, and lack of acknowledg­ement of ground realities.

For its part, DDA, which has prepared the plan with help from the National Institute of Urban Affairs (NIUA), says that the monitoring of the new plan will be stringent. The MPD-2041, officials said, will be evaluated on 20 key performanc­e indicators (KPIS). The assessment will be quantitati­ve, as DDA and NIUA have collected baseline data for all the KPIS, they added.

The MPD-2041 proposes setting up three monitoring committees: Environmen­tal Sustainabi­lity Committee, Built Environmen­t Committee and City Vitality Committee. A senior DDA official said, “These committees will have members from all the agencies concerned. All the three committees will have to submit an annual progress report to an apex committee chaired by Delhi lieutenant governor.”

In addition to annual assessment based on KPIS, the plan also proposes to develop a city-specific liveabilit­y index.

In MPD-2021, too, several groups or committees were proposed for better coordinati­on between all stakeholde­rs, preparing an action plan for transport, streamlini­ng of processes, etc.

AK Jain, former planning commission­er with DDA, said, “But several of the groups were not constitute­d. There were issues related to inter-department coordinati­on, especially related to data. Basic informatio­n that is essential for planning for facilities and upgradatio­n of infrastruc­ture was not available. Monitoring and enforcemen­t were a major problem.”

As per the MPD-2021, local area plans (LAPS) were to be prepared at the municipal ward level and a special redevelopm­ent plan was to be prepared for the Special Areas (which includes the Walled City).

While the municipal corporatio­ns prepared a few LAPS and the redevelopm­ent plan for the special area, these were never notified. Shamsher Singh, former chief town planner with the erstwhile Municipal Corporatio­n of Delhi, said, “There was no clarity on who will notify the special area redevelopm­ent plan. It went back and forth between DDA and the corporatio­n, as the latter didn’t have the power to notify it. LAPS were never notified.”

The MPD-2041 has done away with the provision for LAPS. It proposes to prepare layout plans. Jain said, “LAPS are important for planned developmen­t of an area. There is a need for one agency to monitor the implementa­tion of the master plans.”

Another case in point is the MPD-2021 rejuvenati­on plan for the river Yamuna. Despite a National Green Tribunal order and detailed plan prepared by an expert committee, the plan is nowhere near completion, said Manoj Misra, convener of the Yamuna Jiye Abhiyan.

“The plan was to be implemente­d by 2017,” said Misra. The MPD-2021, Misra said, was not ready on time and then it was revised. “The biggest problem is that suitable changes are made to the master plan as per ground realities. If the plan is constantly altered, then what’s the point of having a master plan?” said Misra.

DDA officials say that the monitoring of progress in MPD-2041 will be stringent. There will also be a Plan Monitoring and Review Unit (PMRU) set up by the DDA that will collect data at regular intervals and manage the GIS database. “We have developed a portal for the MPD-2041. We are in the process of uploading Gisbased

informatio­n about all infrastruc­ture, vacant plots, zonal plans, etc,” said a senior official.

Transit-oriented Developmen­t (TOD) and a land pooling policy, which are aimed at meeting housing requiremen­ts and addressing traffic congestion by bringing work and office spaces closer, were proposed in MPD-2021. But the two are still in the nascent stages of implementa­tion.

While DDA has started work on a TOD project at Karkardoom­a in east Delhi, the land pooling policy is yet to be operationa­lised. The land pooling policy is aimed at meeting the growing requiremen­t for housing in the city. Close to 17 lakh dwelling units will come up in 95 urbanised villages located on the outskirts of the city.

Despite provisions in place, redevelopm­ent in planned areas couldn’t happen.

Sabyasachi Das, former planning commission­er with DDA said, “For the redevelopm­ent, people had to come together, as not many have very large plots in planned areas. But this is not possible. There are also socio-economic issues and property ownership issues. There are multiple concerns due to which redevelopm­ent, even in planned areas, couldn’t happen. The policies have to be flexible.”

 ?? HT ARCHIVE ?? Successive master plans proposed provisions for the rejuvenati­on of the Yamuna. However, the river remains polluted, with most plans still not implemente­d.
HT ARCHIVE Successive master plans proposed provisions for the rejuvenati­on of the Yamuna. However, the river remains polluted, with most plans still not implemente­d.

Newspapers in English

Newspapers from India