ROTATIONAL LOAD SHEDDING ON EMERGENCY BASIS IN NAVI

- Raina Assainar htmetro@hindustant­imes.com

NAVI MUMBAI: In order to avoid a total grid failure in Mumbai Metropolit­an Region (MMR), following the failure of Talegaon Kharghar 400KV line, a rotational load shedding was imposed on emergency basis across Navi Mumbai on Thursday.

A similar grid failure was observed in 2020 in MMR after a line failure due to overload on the remaining power grid. Navi Mumbaikars, hence, had to face close to an hour-long power cuts.

“Due to the issue in the transmissi­on line, Vashi circle had a shortfall of 150MW power. In order to distribute the shortage among every node, all substation­s took a rotational load shedding of close to one hour on Thursday,” an official from Maharashtr­a State Electricit­y Distributi­on Company Limited (MSEDCL), said.

Kharghar, Nerul, Belapur, Koparkhair­ane, Bonkode, Mahape and Turbhe faced power cuts.

On Thursday, at around 6.20am, there was a technical issue in the Talegaon-Kharghar line. “The fault was found at Talegaon. Till 10am, there were no issues but after that, as the commercial institutio­ns started their machinerie­s, and due to the increase in heat, the demand for power increased,” the officer said.

The increased demand for power while there was a failure in Talegaon-Kharghar line led to increased load on the State Load Despatch Centre (SLDC), Kalwa. To avoid a total blackout, SLDC decided for an emergency load shedding that was communicat­ed to MSEDCL to implement.

“During the power outage of 2020, a committee was set up that decided that when a line fails, a distress load shedding should be immediatel­y started to avoid load on other lines resulting in complete failure of other lines as well. Following the same instructio­ns, the load shedding was implemente­d in Navi Mumbai in rotation. While some places had an outage of 30 minutes, some others had it for 45 minutes,” the MSEDCL officer added.

The technical failure in the Talegaon-Kharghar line was rectified by Thursday evening.

“The heat is unbearable. Add to this, when there is a load shedding, it’s a terrible experience. In Kharghar, the power went off twice for a total of three hours,” said Srishti Ghosh Shinde, a Kharghar resident.