Hindustan Times ST (Mumbai) - HT Navi Mumbai Live

49 Kalyan projects lose registrati­on

MahaRERA freezes bank accounts; urges civic authoritie­s to upload CC, OC on dedicated portals

- Satish Nandgaonka­r htmumbai@hindustant­imes.com

UNFAIR TRADE PRACTICES

MUMBAI: In a suo moto action, the state housing regulator, the Maharashtr­a Real Estate Regulatory Authority (MahaRERA), has revoked the registrati­on of 49 projects being probed in Kalyan RERA scam for allegedly submitting fake commenceme­nt certificat­es for “unfair trade practices”, and directed that their designated bank accounts associated with the projects be frozen.

The order by a bench comprising came after a joint hearing at the Bandra Kurla Complex (BKC) headquarte­rs of MahaRERA was held on October 28.

MahaRERA has also directed all department­s to ensure that all statutory certificat­es like Commenceme­nt Certificat­es (CC) and Occupancy Certificat­e (OC) be uploaded immediatel­y on their respective websites, as soon as they are issued. Any changes or modificati­ons thereafter must also be immediatel­y be updated. To further contain the damage done, the authority restrained the promoters of all 49 projects from advertisin­g, marketing, booking, selling or offering any apartment or building for sale in any of these projects. During the physical hearing at the BKC office, only 24 out of 49 promoters or their representa­tives were present. Some of the advocates present sought 1. 2. 3. 4. 5. 6.

Gautam Enterprise­s

Om Sai Developers

Shree Balaji Developers

RMG Infra

Samarth Developers

Shri Shiv Gorakshnat­h Enterprise­s

7. DV Infra

8. Pimpladevi Constructi­on

9. Ms Machindran­ath Enterprise­s

10. Aditya Infra

11. Valku Heritage

12. Vinayak Constructi­on

13. Shiv Sai Balaji Buildcon

14. Vinayak Constructi­on

15. Chirag Constructi­on

16. Ekveera Enterprise­s

17. Saikrupa Developers

18. Ms Sai Developers

19. Gaondevi Constructi­on

20. Shree Swami Samarth Enterprise­s

Shree Samarth Balaji Builders and Developers

22. Narayan Arcade

23. Occean Developers

24. Lakshman Heights

25. Raghukul Heights

21.

more time as a criminal investigat­ion was launched against their clients by Thane crime branch and pleaded that no “precipitat­ory action” be taken against their clients till the investigat­ion is completed. MahaRERA bench heard the advocates, took on record the written submission­s made and reserved its orders.

MahaRERA observed that as per Section 4 of Real Estate (Regulation and Developmen­t) 26. Vagheshwar­i Developers

27. Rudra Heights

28. Saileela Developers

29. Vinayak Enterprise­s

30. Gaondevi Heights

31. Sunshine Developers

32. Tuljabhava­ni Builders and Developers

33. Saijyot Enterprise

34. Shree Sai Chaya Arcade

35. Sanskar Buildcon Builders and

Developers

36. Shree Mahalaxmi Heights

37. Gulmohan Developers

38. Vivaan Heights

39. Balaji Developers

40. Santtula Arcade

41. Om Sai Constructi­on

42. Vishnu Shahu Constructi­on

43. Bama Patil Shopping Centre

44. Expert Home Constructi­on LLP

45. Green Constructi­on

46. Vastu Developers

47. Trijal Enterprise­s

48. Shree Developers

49. Vinayak Vatika Builders and

Developers

Act, 2016, it is mandatory for all promoters seeking project registrati­ons to submit the CC along with other approvals, the sanctioned plan, the layout plan and specificat­ions of the proposed project. The Authority noted that on August 17, 2022, it had received letters from the assistant director, Town Planning, Kalyan Dombivali Municipal Corporatio­n (KDMC) that the CCs of these 49 projects had not been issued by the corporatio­n.

 ?? ??

Newspapers in English

Newspapers from India