Contractor­s who have not done 40% work to get notices

- Eeshanpriy­a M S

MUMBAI: With the deadline for completing desilting of nullahs fast approachin­g and the uproar in the standing committee over misleading claims, the civic body has decided to send showcause notices to four or five contractor­s who have not been able to finish 40% of the work so far. The Brihanmumb­ai Municipal Corporatio­n’s (BMC) decision was made acting on a May 7 status report of desilting works on all nullahs in the city.

Vijay Singhal, the additional municipal commission­er, who heads the stormwater drains (SWD) department, said, “This is a way to pull up these contractor­s up and make sure they speed up the work. It’s like a warning to the contractor­s. However, I am confident that they will be able to complete the decided amount of desilting work before the monsoon.” The BMC wraps up all premonsoon works in the city by May 31 every year. Before the monsoon, it aims to complete 70% of the desilting work, and undertakes the remaining 30% later. “Overall, on an average, 60% of the desilting work has been completed, which is what we had decided for this time of the month. This is good. Some contractor­s are not up to the mark, but this is according to a five-day old report.” Singhal also said this year’s performanc­e so far matches that of the same time, every year.

Overall, on an average, 60% desilting work has been completed so far. VIJAY SINGHAL, additional civic commission­er, BMC

 ?? HT FILE ?? Desilting work was undertaken at the Mithi river near Mahim last week.
HT FILE Desilting work was undertaken at the Mithi river near Mahim last week.