Hindustan Times ST (Mumbai)

Not 2020, Metro-3 tunnelling likely to be completed in 2021

- Tanushree Venkatrama­n

MUMBAI: One of the city’s most ambitious projects, the 33.5-km fully undergroun­d Metro-3 (Colaba-bandra-seepz), has been majorly affected by the coronaviru­s-enforced lockdown. While the Mumbai Metro Rail Corporatio­n (MMRC) was looking at completing tunnelling work by December 2020, lack of labourers, machinery and disruption­s in the supply chain during the lockdown have most likely delayed work to beyond February 2021.

According to officials, MMRC was undertakin­g tunnelling at a speed of 1,500 metre per month before the lockdown, which has reduced to 600m in the past twoand-a-half months. The number of labourers had reduced from 15,000 to 4,000 on site, which has now improved to 6,000 as migrant labourers have started coming to the city. Eighty-three per cent of the tunnelling work and 57% of the overall work have been completed.

A senior official from MMRC said, “There has been a major disruption in the supply chain, availabili­ty of labour and even spare parts. Despite that, we have completed 45.6km of tunnelling work. While we did aim for December 2020 to complete tunnelling work, it might go beyond February 2021 now.” It is the stretch between Mahalakshm­i and Mumbai Central that would spill over to 2021, the official said.

While MMRC was expecting the first rolling stock by December 2020, that might also be delayed owing to the lockdown. The Maharashtr­a Vikas Aghadi (MVA) government, under chief minister Uddhav Thackeray, has also stalled the car-shed work at

Aarey Colony, which would further derail the project. Thackeray stalled the work in November 2019 and appointed a committee to look at alternativ­e options for the car-shed. However, the state is yet to take a call on it.

The earlier deadline for phase 1 of the fully undergroun­d corridor was June 2021, which was revised to December 2021, owing to delays caused by legal battles.

In 2017, MMRC had estimated that even a day’s delay in Metro-3 would cost ₹4.2 crore. The project cost has already escalated from ₹23,000 crore to ₹32,000 crore.

 ?? HT FILE PHOTO ?? 83% of the tunnelling work has been completed.
HT FILE PHOTO 83% of the tunnelling work has been completed.

Newspapers in English

Newspapers from India