Hindustan Times ST (Mumbai)

Dug-up city, pedestrian­s’ nightmare

Road concretisa­tion works in the city have been delayed or altogether abandoned by contractor­s, making walking a hellish experience

- Jeet Mashru htmumbai@hindustant­imes.com

MUMBAI: The BMC’S grand programme to concretise over 400 kilometres of road across the city has not exactly been efficient, drawing the ire of citizens who complain that the haphazard digging has left no space for people to walk. The issue has been highlighte­d and brought to the civic body’s notice on social media, through letters and in a town hall meeting between authoritie­s and local residents. All to no avail. The BMC’S only explanatio­n is that since the utilities below the roads need to be replaced, the process takes time.

Citizens are not buying the argument, pointing out relatively minor projects that have been languishin­g for no apparent reason. For instance, D P Road 9, Powai, a key road in Chandivali that connects lakhs of Chandivali residents to JVLR, has been under concretisa­tion for nearly a year now. The road is less than 600 metres in length. Mandeep Singh Makkar, founder member of the Chandivali Citizen’s Welfare Associatio­n (CCWA), pointed out that the road was narrow to begin with, and the inordinate delay in its concretisa­tion was adding to citizens’ woes. “The work for such an important connector should have been prioritise­d and completed on a war footing,” he said. “Clearly, there is a lack of planning and seriousnes­s in resolving the inconvenie­nce caused to motorists.”

Makkar added that the contractor appointed by the BMC lacked experience in working in traffic-choked cities such as Mumbai. “Project informatio­n boards are missing, and barricades and CCTV cameras are nowhere to be seen,” he said. “All these are part of the agreement and need to be implemente­d.”

In Santacruz East, a road that was started after the last monsoon has been abandoned. “One side was completed and then the work was stopped,” said Gibson Rodrigues, a resident of Kalina. “The footpath either has missing manhole covers or there is constructi­on material dumped on it. Hundreds of children from the three schools in this area have been forced to walk on the road.”

Rodrigues added that the roads in his area had not been swept even once after the road concretisa­tion was done. “Senior citizens and children are the worst affected,” he said. “Many have developed allergies on account of the constant dust clouds. Since there are no municipal councillor­s for the last two years, citizens’ health has gone for a toss.”

The BMC, during its budget estimates in February, had stated that 397 kilometres of road were under concretisa­tion. “This also includes utility ducts and laying utility cables to reduce frequent digging,” it had stated. The civic body had then said that concretisa­tion works on 252 kilometres of road, including last year’s spillover, had been completed, and it was in the process of issuing tenders to concretise 209 kilometres of road in the coming financial year. The menace is not limited to the suburbs. Activists and local citizens complain that the incomplete concretisa­tion works and missing traffic wardens are causing chaos in many parts of Dadar. “There are no proper barricades, manholes are kept open and there are no ramps for senior citizens,” said Chetan Kamble, founder of citizens’ group Chakachak Dadar. “There are no traffic wardens to manage traffic. The entire stretch is filled with dust pollution.”

Suryakant Naik, a food seller on Kakasaheb Gadgil Marg in Dadar West, said that not only was he losing business due to the constant dust clouds, it was becoming difficult for residents to even walk on the road. “Previously, the road was being watered daily,” he said. “But that too has stopped for a month now. The work has been left incomplete and there is no space at all for walking.”

A s e n i o r B MC o f f i c i a l explained that utilities below the road had to be shifted in the concretisa­tion process, which was causing the delays. “For example, if there is a high-tension cable below the road, one has to find a way to lay it again,” he said. “Then there are water pipelines and other things that need to be shifted. This takes time. We hold joint meetings at the ward level to ensure faster coordinati­on.” Dhawal Ashar, programme head of urban transport and road safety at the non-profit World Resources Institute, India, said that before concreting every stretch of Mumbai, be it entire carriagewa­ys or just side strips, utility works needed to be first undertaken by the BMC. “These works are almost all the time on the edges of the road; footpaths are demolished, making walking extremely difficult,” he said. “But in a city where more than half the travel is in the form of walking, the BMC needs to ensure that there is space to walk at all times and under every circumstan­ce, like there is for automobile­s. Priority needs to be given to pedestrian­s.”

A BMC official, when questioned, maintained that once projects were taken up, they did not need more than 45 to 60 days, and hence there was no need to create separate space for pedestrian­s. “The delay that is happening is because many roads have been handed over to a single contractor, leading to a shortage of labour at a few places,” he said. “With festivitie­s like Holi and Ramzan ahead, when workers go back to their villages, there may be a further shortage.”

 ?? SATISH BATE/HT PHOTOS ?? DP ROAD 9, CHANDIVALI: The road has been under concretisa­tion for nearly a year now.
SATISH BATE/HT PHOTOS DP ROAD 9, CHANDIVALI: The road has been under concretisa­tion for nearly a year now.
 ?? ?? VILE PALE EAST: There’s hardly any space left for commuters to walk outside the station due to dug-up road
VILE PALE EAST: There’s hardly any space left for commuters to walk outside the station due to dug-up road

Newspapers in English

Newspapers from India