Khar flyover: Junked in ’18, ‘necessary’ now

BMC has merely changed the name of the project from ROB to elevated road, say enraged residents

- Linah Baliga leena.baliga@htlive.com

MUMBAI: The Brihanmumb­ai Municipal Corporatio­n’s (BMC) current plan of building an elevated road over Khar Subway was rejected by the civic body in 2018 owing to hindrances and a sharp 90-degree turn along the path. Residents’ groups in the area, who have been opposing the proposed project, accused the BMC of merely changing its name from a road over bridge (ROB) to an elevated road, and wondered if the civic body was deceiving citizens back then or now. BMC officials agreed the project was scrapped earlier as it was not feasible, but said it was being brought back due to urgent requiremen­t of citizens.

The Khar Subway is very narrow and gets waterlogge­d frequently. Though only light motor vehicles are permitted, traffic jams are common in the subway and along approach roads on either side. Owing to these reasons, residents of Santacruz and Khar have been demanding an alternativ­e eastwest connector over the railway tracks for years.

On May 10, 2016, local MLA Ashish Shelar visited the area and requested for an ROB over Khar Subway.

The BMC’S bridges department subsequent­ly appointed TPF Engineerin­g Pvt Ltd as a consultant to study the feasibilit­y of such a project.

The report submitted on July 31, 2018 stated that there were a lot of hindrances along the path of the proposed ROB, with permanent buildings and encroachme­nts at Abdul Hakim Chowk, where it takes a sharp 90-degree left turn.

The report stated, “It was observed that a portion of existing structures including Willingdon Catholic Gymkhana are encroachin­g the alignment of the road. Also, on east side, there is sharp 90-degree left turn which is encroached by a number of permanent buildings and hutments. In the view of the above, it is not possible to move ahead for the ROB.” Based on this report, the BMC shelved plans of building an ROB over the subway.

The new project proposal prepared by BMC shows its alignment is largely similar to the one rejected in 2018 – it manoeuvres through narrow roads going past schools, hospitals, and gardens, and takes a sharp 90-degree left turn at Abdul Hakim Chowk.

Advocate Trivankuma­r Karnani, founder of MNCDF, said, “The BMC’S own report in 2018 clearly mentioned that it isn’t feasible to construct the flyover over Khar Subway because there is a sharp 90-feet left turn at Abdul Hakim Chowk. They are clearly contradict­ing their own report now.”

In the new design too, there is a sharp 90-degree turn at the same spot, where there are buildings and encroachme­nts that will hinder the placement of bridge pillars, the advocate noted.

“Either the BMC was fooling us then or it is deceiving us now,” he alleged, adding, “They have merely changed the name of the project from ROB to elevated road.”

When asked about the 2018 report, on basis of which the BMC shelved plans of constructi­ng an ROB over Khar Subway, he said,

“We are aware that we had junked the project because it was not feasible due to its alignment and the 90-degree turn at Abdul Hakim Chowk. But now, we are doing it because there is an urgent need from citizens, who are demanding this flyover.”

 ?? ??